• insights-banner

    In the Press

Melanie Tomlin explains the measure of damages recoverable in defects claims for Building Magazine

min read

In the fourth article of the essential law series which looks at the topic of defects, Melanie Tomlin, Senior Associate, explains the measure of damages recoverable in defects claims. Read her article below, first published in Building Magazine. 

Damages for breach of contract usually seek to compensate the claimant for the loss caused by the breach. But where a builder carries out work defectively, how should those damages be assessed? Some principles are set out below.

The aim of awarding damages is to put the claimant into the same financial position as if the contract had been properly performed.

The general rule is that damages compensate for financial loss, such that damages are not awarded for mental distress or other non-financial losses. This is subject to some limited exceptions, one of which is considered below.

Cost of rectification versus diminution in value

So, what is the measure of damages where a builder carries out work defectively?

In seeking to put the owner into the same position as if the contract had been properly performed, the owner might be awarded a "cost of rectification" measure or a "diminution in value" measure.

The former is where the owner is awarded the cost of engaging someone else to complete or rectify the work. The latter is where the owner is awarded the difference in value between the property as it should have been if the contract had been properly performed and its actual value.

Where there is a choice between the two measures in a defects claim, the cost of rectification will generally be awarded unless it would be so wholly disproportionate to the benefit of remediating the defects as to make it unreasonable.

Even where the cost of rectification greatly exceeds the difference in the property's value, on certain facts the owner may be entitled to that cost, provided that:

  • The owner has rectified or intends to rectify. (Where the court is basing itself on the owner's intentionto rectify, it cannot be absolutely sure that this is what the owner will do although the court has found that probable intention would be sufficient. That said, there is of course no claw-back of damages if ultimately the owner decides to spend them on something else); and
  • It would not be unreasonable in the circumstances to award the higher cost of rectification.

These principles are illustrated in the leading case of Ruxley Electronics and Construction Ltd vs Forsyth.

Mr Forsyth contracted to have a swimming pool built with the depth at the deep end of 7ft 6in. When built, the pool was in fact only 6ft 9in at the deep end. Nevertheless, it was still perfectly safe for swimming and diving so that the resale value of the property was not affected by the admitted breach of contract. By contrast with the nil difference in value, the cost of rectification (to increase the depth of the pool to the agreed depth) would be £21,000.

The House of Lords refused to award Mr Forsyth the cost of rectification of £21,000; that would be unreasonable, because it was disproportionate to the nil difference in value. In addition, it was relevant that the first instance judge had found that Mr Forsyth had no intention to use the damages to rebuild the pool.

Loss of amenity

Somewhat controversially, rather than awarding Mr Forsyth no damages at all, the House of Lords awarded damages of £2,500 for "loss of amenity".This appears to fall within the category of damages for mental distress where the predominant (or an important) object of the contract is mental satisfaction - one of the limited exceptions where non-financial loss can be recovered. Mr Forsyth's diving was not as pleasurable as it would have been had the pool been the depth contracted for.

As a general rule, an award of loss of amenity would only be available to an individual, not a company, because non-financial loss is, by its very nature, only capable of being experienced by humans.

Can a claimant be entitled to rectification costs and damages for diminution in value? Yes, there are circumstances where even though a defect has been rectified, the property has been blighted such that its value is less than would have been the case if there had been no defect in the first place.

Other types of damages

There are other types of losses that may be suffered by a claimant (in addition to the cost of reinstatement or diminution in value) that could be recovered in a defects claim.

These include loss of profit, alternative accommodation costs, management expenses, and damages for "distress and inconvenience". Such damages are not ordinarily recoverable in a commercial contract but could be recovered in a residential context.

The full article was first published in Building Magazine (subscription required).

Our thinking

  • Getting The Most From Your People

    Megan Paul

    Events

    min read
  • London Arbitration Week: ‘Building Data Centres Without Building Disputes’

    Gareth Mills

    Events

    min read
  • Construction Market Update: Looking Forward

    Michael O'Connor

    Events

  • Should You Even Bother? Making the Case for Bringing a Case

    Caroline Greenwell

    Events

    min read
  • Britain wants nuclear: Can we build it at pace?

    Kevin Gibbs

    Events

    min read
  • After the Confetti: Why the Real Work Begins the Day After Listing

    Greg Stonefield

    Insights

    min read
  • Investors’ Chronicle quotes Tamasin Perkins on how to avoid invalidating a will

    Tamasin Perkins

    In the Press

    min read
  • Ready for 2027: Legal Developments Shaping the Living Sector in England

    Mark White

    Insights

    min read
  • Q&A: Right to manage: can a landlord object on procedural grounds?

    Lauren Fraser

    Insights

    min read
  • Investing in London Real Estate Seminar

    Chiara Del Frate

    Events

    min read
  • Beds, Meds and Sheds: the beds haven’t gone – they’ve moved into houses

    Mark White

    Insights

    min read
  • Charles Russell Speechlys advises longstanding client SaxaVord Spaceport on its £30m investment from the UK government

    Charlie Ring

    News

    min read
  • Q&A: Recovering a freehold

    Sylwia Barchus

    Insights

    min read
  • Evidencing oral agreements: the weight of words

    Ben Moore

    Insights

    min read
  • Budget 2026: what the energy measures mean for generators, industry and investors

    Kevin Gibbs

    Insights

    min read
  • Nicola Saccardo comments on Italy’s proposed exit tax regime for wealthy individuals in The Daily Telegraph

    Nicola Saccardo

    In the Press

    min read
  • Loss of bargain on contract cancellation: no repudiatory breach required

    Mary Barrett-Jones

    Insights

    min read
  • ICLG quotes Dewdney William Drew on the High Court’s PINK trade mark ruling

    Dewdney William Drew

    In the Press

    min read
  • Amy Shuttleworth and Nicholas Wyatt write in RICS Property Journal about electric vehicle charging point leases

    Amy Shuttleworth

    In the Press

    min read
  • The Law Society Gazette quotes Kerry Stares on the development of the AI-powered Pro Bono Family Justice Hub

    Kerry Stares

    In the Press

    min read
Back to top