• insights-banner

    In the Press

Melanie Tomlin explains the measure of damages recoverable in defects claims for Building Magazine

min read

In the fourth article of the essential law series which looks at the topic of defects, Melanie Tomlin, Senior Associate, explains the measure of damages recoverable in defects claims. Read her article below, first published in Building Magazine. 

Damages for breach of contract usually seek to compensate the claimant for the loss caused by the breach. But where a builder carries out work defectively, how should those damages be assessed? Some principles are set out below.

The aim of awarding damages is to put the claimant into the same financial position as if the contract had been properly performed.

The general rule is that damages compensate for financial loss, such that damages are not awarded for mental distress or other non-financial losses. This is subject to some limited exceptions, one of which is considered below.

Cost of rectification versus diminution in value

So, what is the measure of damages where a builder carries out work defectively?

In seeking to put the owner into the same position as if the contract had been properly performed, the owner might be awarded a "cost of rectification" measure or a "diminution in value" measure.

The former is where the owner is awarded the cost of engaging someone else to complete or rectify the work. The latter is where the owner is awarded the difference in value between the property as it should have been if the contract had been properly performed and its actual value.

Where there is a choice between the two measures in a defects claim, the cost of rectification will generally be awarded unless it would be so wholly disproportionate to the benefit of remediating the defects as to make it unreasonable.

Even where the cost of rectification greatly exceeds the difference in the property's value, on certain facts the owner may be entitled to that cost, provided that:

  • The owner has rectified or intends to rectify. (Where the court is basing itself on the owner's intentionto rectify, it cannot be absolutely sure that this is what the owner will do although the court has found that probable intention would be sufficient. That said, there is of course no claw-back of damages if ultimately the owner decides to spend them on something else); and
  • It would not be unreasonable in the circumstances to award the higher cost of rectification.

These principles are illustrated in the leading case of Ruxley Electronics and Construction Ltd vs Forsyth.

Mr Forsyth contracted to have a swimming pool built with the depth at the deep end of 7ft 6in. When built, the pool was in fact only 6ft 9in at the deep end. Nevertheless, it was still perfectly safe for swimming and diving so that the resale value of the property was not affected by the admitted breach of contract. By contrast with the nil difference in value, the cost of rectification (to increase the depth of the pool to the agreed depth) would be £21,000.

The House of Lords refused to award Mr Forsyth the cost of rectification of £21,000; that would be unreasonable, because it was disproportionate to the nil difference in value. In addition, it was relevant that the first instance judge had found that Mr Forsyth had no intention to use the damages to rebuild the pool.

Loss of amenity

Somewhat controversially, rather than awarding Mr Forsyth no damages at all, the House of Lords awarded damages of £2,500 for "loss of amenity".This appears to fall within the category of damages for mental distress where the predominant (or an important) object of the contract is mental satisfaction - one of the limited exceptions where non-financial loss can be recovered. Mr Forsyth's diving was not as pleasurable as it would have been had the pool been the depth contracted for.

As a general rule, an award of loss of amenity would only be available to an individual, not a company, because non-financial loss is, by its very nature, only capable of being experienced by humans.

Can a claimant be entitled to rectification costs and damages for diminution in value? Yes, there are circumstances where even though a defect has been rectified, the property has been blighted such that its value is less than would have been the case if there had been no defect in the first place.

Other types of damages

There are other types of losses that may be suffered by a claimant (in addition to the cost of reinstatement or diminution in value) that could be recovered in a defects claim.

These include loss of profit, alternative accommodation costs, management expenses, and damages for "distress and inconvenience". Such damages are not ordinarily recoverable in a commercial contract but could be recovered in a residential context.

The full article was first published in Building Magazine (subscription required).

Our thinking

  • IBA Annual Conference 2026

    Jean-Baptiste Beauvoir-Planson

    Events

  • Child Maintenance: Reform, a Key Appeal, and the Elusive Christmas Order

    David Carver

    Quick Reads

    min read
  • High Court interprets repair covenant in Hotel lease and statutory fire safety obligations

    Chandni Pandya

    Insights

    min read
  • Be Careful What You Wish For: In the UAE, How a Tenant’s Force Majeure Claim Can Dissolve Its Own Lease

    Glenn Bull

    Insights

    min read
  • PISCES Platforms Update: Wayve Marks a Milestone as a Fourth Operator Enters the Sandbox

    Greg Stonefield

    Insights

    min read
  • Building safety update: Progress on future changes, including the recategorisation of certain higher risk building works

    David Savage

    Insights

    min read
  • Drapers quotes Cara Imbrailo on out-of-town retail parks and fashion retailers' need for space

    Cara Imbrailo

    In the Press

    min read
  • Georgina Muskett contributes to PropLaw on the Landlord and Tenant Act and opposing lease renewal on the ground of redevelopment

    Georgina Muskett

    In the Press

    min read
  • In-House Insights: Next Gen Drinks Reception

    Events

    min read
  • Lauren Fraser comments in PropLaw on reforms to property ownership in the UK through commonhold tenure

    Lauren Fraser

    In the Press

    min read
  • Ben Smith writes in Employee Benefits about how debate over statutory menstrual leave could impact workplace policy

    Ben Smith

    In the Press

    min read
  • The Final Countdown: Practical Steps for Employers Ahead of January 2027

    Francesca Charlton

    Quick Reads

    min read
  • Charles Russell Speechlys Opens New York Office and Connecticut Practice

    Simon Ridpath

    News

    min read
  • Planning committees – a new national scheme of delegation

    Sadie Pitman

    Quick Reads

    min read
  • Disputes Over Donuts: Sports Arbitration

    Jue Jun Lu

    Podcasts

  • Why domicile still matters after the 2025 IHT changes

    Harriet Betteridge

    Insights

    min read
  • Charles Russell Speechlys further bolsters Private Equity expertise with the appointment of James Paterson

    David Collins

    News

    min read
  • Charles Russell Speechlys shares practical framework for choosing the right legal AI tools

    Lesley O’Leary

    News

    min read
  • Sadie Pitman writes in CoStar about the development of hyperscale data centres

    Sadie Pitman

    In the Press

    min read
  • Rebecca Morjaria is quoted in the press about our role advising Mulalley & Co. in a successful £1.8m Building Safety claim

    Rebecca Morjaria

    In the Press

    min read
Back to top