Top 10 tips for developers dealing with retentions and escrow agreements

min read

Retentions and escrow agreements can be useful mechanisms in a sale or purchase of a development site to cover the risk of payments or works which need to be carried out by the other party. This article focuses on retentions and escrows used by purchasers/developers in the course of land transactions, but they are also used in a corporate and construction context.

1. What is the difference between a retention and an escrow?

A retention is a sum which is “retained” from the purchase price, usually by the purchaser. It will not be released to the seller until a trigger has occurred under the contract.  But it will still form part of the purchase price paid at completion.  An escrow is an agreement under which funds are held.

2. Why do you need a retention? (1) Works and payments

They are mostly used on purchases of a parcel which forms part of a wider scheme, where the purchaser is relying on the seller to carry out works for the benefit of that parcel, or make payments that affect the development of that parcel.  The money held as a retention can then be used where those works are not carried out within the timescales required and a developer has to “step-in” see below). Can also be used to cover off a risk of e.g. an unanticipated s106 payment or CIL.

3. Why do you need a retention? (2) Covenant strength of seller

Where the seller is e.g. an SPV with limited assets, or the value of works, or the amount of payments, are high, there will be limited recourse for recovering expenditure from them. A retention offers certainly for recovery of costs.

4. How much should a retention be?

The retention must be sufficient to cover off costs of any works or payment. This requires considerable input up front to scope the cost of works and ensure that the retention is sufficient. The contract should also provide that where costs more than the retention then the seller has to repay the “shortfall” to the purchaser.

5. Step in rights

It is all well and good having a pot of money out of which you can deduct your costs but a developer needs to ensure that if they are carrying out works to third party land they have sufficient step-in rights to by way of licence or easements. To avoid occupation restrictions or the site being ransomed by non-completion of access or servicing works. 

6. Triggers for deduction from the retention

The parties need to be clear what the trigger for the deduction from the retention is and return of the balance (if any). E.G. Practical completion of works or evidence of payments.

7. SDLT considerations in respect of a retention

As above, the retention forms part of the purchase price and will attract stamp duty land tax.   You may apply to HMRC to defer the SDLT on the retention (on the basis that it is a contingent amount). Or if SDLT was paid on the entirety of the purchase price including the retention, the purchaser might be able to apply to HMRC to recover the SDLT paid on the retention by amending its SDLT return in the 12 month window. Once this has passed, the purchaser cannot recover the SDLT paid on the amount of any retained payment.

8. VAT considerations in respect of a retention

If the seller has opted to tax then VAT will also be payable on this retention. As the VAT is usually paid on completion SDLT will need to be paid on the whole amount of the VAT, and deferred as above if possible. But ensure your cash flow accounts for VAT.

9. What are the terms of the escrow agreement?

Consider whether or not (1) you will hold the retention – this is better for cash flow (2) it will be held by your solicitors (and whether this can be achieved under the Solicitors Accounts Rules) or (3) if it will be held by a third party escrow agent (if so, who covers the costs?).

10. Control of release of release of the retention from the escrow

The parties will need to consider who controls the release of funds e.g. does evidence need to be provided to, or from, an independent third party? Or do both parties just have to agree it is released? How soon the funds need to be made available will be a key consideration for this point. If there is a disagreement as to release of funds the parties need to consider how this will be resolved i.e. will it be referred for expert determination?


For more information on the above please contact Anna Donnelly, Suzi Gatward or your usual Charles Russell Speechlys contact.

Our thinking

  • IBA Annual Conference 2026

    Jean-Baptiste Beauvoir-Planson

    Events

  • Surveyors' Refresher Seminar

    Hope Barton

    Events

    min read
  • Building Safety Update Seminar

    David Savage

    Events

    min read
  • Succession, governance and the next generation in US Family Offices

    Hugh Dixon

    Quick Reads

    min read
  • Why the UK-India Trade Deal Matters for Private Capital

    Kim Lalli

    Quick Reads

    min read
  • Wei Kang comments on China’s new tax rule on offshore trusts in The Straits Times

    In the Press

    min read
  • A New Era of Wealth and Estate Planning for PRC High-Net-Worth Families

    Wei Kang

    Insights

    min read
  • What Wadworth Tells Us About the Next Phase of PISCES

    Greg Stonefield

    Insights

    min read
  • Supply chain social audits: what they are, their limitations, and why they matter for human rights due diligence

    Kerry Stares

    Insights

    min read
  • Summer 2026 Update: Where are we are on the Government’s roadmap to Commonhold?

    Laura Bushaway

    Quick Reads

    min read
  • Leasehold and Freehold Reform Act 2024: New consultations on valuation and legal costs of enfranchisement and lease extension claims

    Laura Bushaway

    Quick Reads

    min read
  • Leasehold Reform; Government responds to consultation on service charge regulation

    Laura Bushaway

    Quick Reads

    min read
  • Building Safety Levy: What Do the Proposed 2026 Amendments Mean?

    Mark Barley

    Insights

    min read
  • Autumn Budget 2026: possible CGT changes and pre-budget planning

    Julia Cox

    Insights

    min read
  • Family team successfully represent high-profile businessman in High Court jurisdiction dispute case

    Matt Foster

    Quick Reads

    min read
  • Private capital, succession planning and cross-border wealth complexity in Asia

    Kevin Lee

    Insights

    min read
  • Can you terminate an “indefinite” trade mark licence even if there’s no express right to do so?

    Isabella Ross-Skinner

    Insights

    min read
  • Technology, AI and US Family Offices

    Hugh Dixon

    Quick Reads

    min read
  • Reaz Jafri quoted in CNBC on EU crackdown on Caribbean "golden passport" programmes

    In the Press

    min read
  • Shaping the Future of AIM: What the New AIM Rules Mean for Growth Companies, Founders and Advisers

    Paul Arathoon

    Insights

    min read
Back to top