• news-banner

    Expert Insights

“Subject to Contract” does not amount to an agreement

My colleagues Anna Sowerby and Eveline Strecker recently commented on the case of Joanne Properties Limited v Moneything Capital Limited where the Court of Appeal overturned a decision of the lower court which had found that a binding agreement had been arrived at despite communications being labelled “subject to contract” during settlement negotiations: Subject to contract’ – The effect of these words in settlement negotiations.

A recent case in the Technology and Construction Court has reinforced the message that labelling communications “subject to contract” will generally prevent an agreement coming into force.

Section 108(3) of the Housing Grants, Construction and Regeneration Act 1996 states that:

“…the decision of the adjudicator is binding until the dispute is finally determined by legal proceedings, by arbitration (if the contract provides for arbitration or the parties otherwise agree to arbitration) or by agreement” [emphasis added].

In Aqua Leisure International Limited v Benchmark Leisure Limited the court had to decide whether the conduct of the parties amounted to an agreement so that the adjudicator’s decision was no longer binding and therefore incapable of enforcement.

Background facts

Aqua Leisure was successful in an adjudication in July 2017 in relation to an interim application for payment.  Following that decision, the parties met to discuss and agree the final settlement of the account, including release of any retention which was subsequently due to Aqua Leisure.

On 31 August 2017, agreement was reached via a telephone conversation between the principals of the parties.  This was recorded in an email exchange between the principals which was expressly stated to be without prejudice and subject to contract.

The agreed terms were for staged payments to be made by Benchmark, for Aqua Leisure to complete the “warranty works” and for a payment of £110,000 to be guaranteed by Benchmark’s parent company.  Some of these stage payments were subsequently made by Benchmark, albeit not strictly within the deadlines stipulated in the parties’ agreement.

In the interim, Aqua Leisure circulated a settlement deed and asked Benchmark to execute it.  The terms of the settlement deed did not reflect the entirety of the parties’ agreement of August 2017 and instead sought to increase the payment that the parent company was guaranteeing.   Benchmark never signed the settlement deed and on 11 May 2018 confirmed that there would be no parent company guarantee.

The sums awarded under the adjudication were not paid in full and the payments due under the staged payment regime agreed by the parties in August 2017 were also not paid in full.

Aqua Leisure therefore applied to the court to enforce the adjudicator’s decision in April 2019.

The court’s decision

The adjudicator’s decision was enforced by the Technology & Construction Court.  In doing so the judge noted that the parties had clearly agreed in August 2017 that there would be no binding contract until the terms were reduced to writing and signed off.  This was clear by the words “subject to contract” in the email communications around that time, as well as Aqua Leisure’s subsequent chasing of Benchmark for execution of the agreement.

The court held that the question was whether (after the email exchange in August 2017), the parties had agreed to enter into a binding contract (a new contract) without the need for all terms to be reduced to writing.  The court found that there nothing in the points advanced by the defendant that allowed a conclusion that a new contract was made.

The judge was not persuaded by the fact that stage payments had been made by Benchmark and that Aqua Leisure had carried out the warranty works.  The judge pointed out that in the absence of a compromise, sums were still due under the original contract and under the terms of the binding adjudicator’s award.  Payments made and work carried out was therefore not evidence of a new contract having come into existence but rather simply evidence that the parties were working together to settle debts and obligations under the original contract.

The Late Payment of Commercial Debts (Interest) Act

This case also confirmed the previous position that an adjudicator cannot award legal costs pursuant to the Late Payment of Commercial Debts (Interest) Act 1998.  The court severed the aspects of the adjudicator’s decision awarding costs, finding that the adjudicator had no jurisdiction to make such an award.

Practical tips

Due care must always be taken by parties seeking to compromise matters arising out of an adjudicator’s decision.  If communications are labelled as “subject to contract” and no formal agreement has been executed, it is likely that a court will find that the parties have not reached a binding agreement.  Until such time as a binding settlement agreement has been reached, the parties would be well advised to treat the adjudicator’s decision as binding.

Care should also be taken to carefully record the terms of any oral agreement between the parties and to then ensure that any subsequent settlement agreement accurately reflects that agreement. 

For more information please contact your usual Charles Russell Speechlys contact. 

Our thinking

  • Mental Health Management

    Nick Hurley

    Events

  • Calculating Social Value in BTR

    Francis Ho

    Events

  • Dangers of trusts

    Mark Summers

    Events

  • In-House Insights

    Megan Paul

    Events

  • Heritage property and conditional exemption

    Sarah Wray

    Insights

  • Stamp Duty Refund - New Impetus To Eligible Incoming Talents

    Ian Devereux

    Insights

  • City AM quotes Gareth Mills on the CMA’s new set of principles for regulating AI

    Gareth Mills

    In the Press

  • Hamish Perry and Mike Barrington write for The Evening Standard on whether a merger between the CBI and Make UK can work

    Hamish Perry

    In the Press

  • Silicon quotes Gareth Mills on the UK consumer lawsuit against Google

    Gareth Mills

    In the Press

  • Common construction claims in Bahrain

    Mazin Al Mardhi

    Insights

  • Property Week quotes Louise Ward on the additional support required by aspiring UK life sciences operators

    Louise Ward

    In the Press

  • Sarah Higgins and David Wells-Cole write for Wealth Briefing on the pitfalls of using unregulated legal services

    Sarah Higgins

    In the Press

  • Charles Russell Speechlys’ UK offices receive environmental certification

    Kerry Stares

    News

  • Case analysis: URS Corporation Ltd V BDW Trading Ltd

    James Worthington

    Insights

  • True value adjudications; don’t jump the gun!

    Christopher Busaileh

    Insights

  • Financial Reporter quotes Rhys Novak on a new FCA review into the treatment of PEPs

    Rhys Novak

    In the Press

  • In-House Insights Programme 23/24

    Megan Paul

    Events

  • Restrictive covenants – who has the benefit?

    Georgina Muskett

    Insights

  • First time buyers relief and trusts

    Sarah Wray

    Insights

  • City AM quotes Ashwin Pillay on the latest round of ONS M&A statistics

    Ashwin Pillay

    In the Press

Back to top