• news-banner

    Expert Insights

The balance between Fairness and Certainty in UAE Construction Contracts

For common law practitioners new to the UAE, Articles 106, 246 and 390 of the UAE Civil Code are features of UAE law that takes some adjustment and require understanding. These provision state that a person can be liable for the unlawful exercise of an explicit right in the contract (Art. 106); that the contract must be performed in good faith and in accordance with local custom (Art. 246); and that compensation can be fixed in advance but then adjusted by the court if necessary (Art.390). Such provisions, from a common law practitioner’s perspective, will immediately be seen as creating uncertainty in the contract. Therefore, when giving advice, common law lawyers need to adopt a different approach to contract interpretation.

Judges and arbitrators applying the law of the UAE can at times have a wide discretion to reach an outcome that he or she believes to be a “fair outcome”, despite in some respects, the decision contradicting the explicit terms of the contract.

On a practical level, such provisions create some uncertainty, as in most situations, what is fair and reasonable is subjective, with a lot of grey areas. This can create an incentive for a party who took a commercial risk that didn’t pay off, to instigate proceedings in the hope of being bailed out of its mistake by a sympathetic tribunal. The party most often able to benefit here is the contractor.

Article 246 states as follows:

  1. The contract must be performed in accordance with its contents, and in a manner consistent with the requirements of good faith.
  2. The contract shall not be restricted to an obligation upon the contracting party to do that which is [expressly] contained in it, but shall also embrace what is appurtenant to it by virtue of the law, custom, and the nature of the disposition.

Again, despite what has been explicitly agreed in the terms of the contract, considerations around ‘good faith’, ‘what is appurtenant’ (also translated as an “essential requirement”) and ‘customs consistent with the nature of the disposition' all impact on how such terms can and will be applied. The construction industry is one of the most impacted by such law, as few industries have such ingrained customs. Such customs are often adopted, despite the terms of the contract, as the engineer and the parties naturally follow their own favoured procedures and precedent forms.

Article 106(2) also provides another clear example of the court being able to prohibit the enforcement of terms explicitly agreed in the contract. It provides that the exercise of a right will be unlawful in any one of the following circumstances: when (i) the intention is to harm others; (ii) the intended gain is of little importance when compared to the damage caused to the other; (iii) the exercise of the right exceeds what is usually accepted by custom and usage; or (iv) such exercise is contrary to the provisions of Islamic Shari’ah, public policy or morals.

When it can be shown that there is an intention to cause harm, the moral argument for such provision is convincing. However such cases are likely to be rare, as proving such intent is often going to be extremely difficult. Furthermore, Article 106(2) applies to a much wider array of situations, creating real uncertainty as to how the contract will be applied where one party faces significant losses, or even ruin, due to:

  • a calculated commercial gamble that it lost; or
  • its own negligence, agreeing to terms of a contract that it knew it could never fulfil

Article 106 in this instance essentially provides such party with a very real chance of remedying the situation at the back end of the deal, once the agreement has been implemented and the risk has arisen. As such, contractors can and will take bigger risks in what they sign up to, and employers who adopt unfair and unreasonable contractual terms are left with real uncertainty as to whether or not such terms can be enforced. The resulting situation is that neither party proceeds with confidence in, or ultimately will give reverence to, the contract.

Another prime example of the court having such discretion is article 390(2), which provides that in all cases of the parties having agreed to fix a sum for liquidated damages, the court can, at the request of either party amend such agreement in order to make the amount assessed equal to the loss suffered.

As such, any agreement reached in the contract negotiations can be set aside to represent the actual loss. The contractor’s risk is in effect uncapped, but its price will often not take such risk into account. Negotiations on liquated damages can be hard fought, with give and take applied to the rate of liquidated damages resulting in movement in the contract price, with neither party acknowledging or perhaps realising that the court will have discretion at the conclusion of the works to re-assess the entire sum.

So what is the solution? Ideally, these provisions of the civil code should encourage employers to tender with contracts that are fair and reasonable, and ensure that their engineer’s administer them accordingly. This however is rarely the case, as contracts weighted heavily in favour of the employer are still common practice. Where this is the case, the employer and engineer need to be extremely careful and consistent with their application of the contract, ensuring that they are at all times clear and consistent, ensuring the contractor is aware of the strict obligations agreed. Seeking to enforce stringent or harsh terms only at the point of terminating a contract or seeking to make deductions from the final account creates a real risk of a challenge by the contractor.

Our thinking

  • Updates from the Building Safety Regulator - Unblocking the Gateways for Higher Risk Buildings

    Tegan Johnson

    Quick Reads

  • What do agricultural landlords and workers need to know about the Renters’ Rights Act?

    Emma Preece

    Insights

  • What legal developments can the Living Sector expect as we approach the end of 2025 and look ahead to 2026?

    Mark White

    Insights

  • Andrew Ross and Laura Bushaway write for Property Week on a Supreme Court judgment relating to nuisance

    Andrew Ross

    In the Press

  • Charles Russell Speechlys further bolsters its Corporate team with the appointment of Ed Morgan

    David Collins

    News

  • Adjudication under the Construction Act – a case on the residential occupier exception and contesting the validity of a payless notice

    Tegan Johnson

    Insights

  • VAT on Developer’s Biodiversity net gain (BNG) costs

    Elizabeth Hughes

    Insights

  • Understanding the Fire Safety (Residential Evacuation Plans) (England) Regulations 2025: The Living Sector

    David Savage

    Insights

  • Law Middle East quotes Thomas Snider and Dalal Alhouti on the UAE’s rise into the top five seats of arbitration in the International Chamber of Commerce (ICC) International Court of Arbitration

    Thomas R. Snider

    In the Press

  • James Broadhurst writes for Family Office Magazine on the attractiveness of hotels as an asset class

    James Broadhurst

    In the Press

  • Construction News quotes David Savage on the latest round of administration statistics in the construction sector

    David Savage

    In the Press

  • What role can construction lawyers play in helping UK construction sector clients achieve greater success and how?

    David Savage

    Insights

  • Dubai Law No. 7 of 2025: Regulatory Shifts in the Contracting Sector

    Paula Boast MBE

    Quick Reads

  • Disputes Over Donuts: Mediation - An International Perspective

    Tamasin Perkins

    Podcasts

  • In-Depth Virtual Currency Regulation

    Sara Sheffield

    Insights

  • IBA Annual Conference 2025

    Simon Ridpath

    Events

  • Installing Chinese Turbines in European Wind Projects – what do you need to know?

    Jue Jun Lu

    Insights

  • Public Policy in International Arbitration

    Peter Smith

    Insights

  • Updates to the Planning Practice Guidance relating to the Green Belt

    Titilope Hassan

    Insights

  • Heritage Partnership Agreements: the future of historic buildings?

    Sophie Willis

    Quick Reads

Back to top