The Gulf diplomatic dispute and construction claims - extensions of time
As Qatar continues its progresses towards the 2022 FIFA World Cup and the development strategy for the 2030 National Vision, the current diplomatic dispute occurring in the Gulf is impacting on many parties involved in construction projects occurring throughout the nation.
The question concerning many of these parties, whether consultants, contractors, sub-contractors, suppliers or employers, relates to claims and what relief, if any, the parties are entitled to under their respective contracts.
In this article, we will look at the Contractor’s right to an extension of time under the FIDIC suite of contracts where that extension of time has been caused by the late supply of goods being shipped to Qatar through the UAE.¹ Following the commencement of the diplomatic dispute, many Contractors have suffered delayed as a result of goods having to be shipped from the UAE to Oman before they could be transferred to a vessel that would deliver the goods onward to Qatar.
Clause 8.4(d) of the FIDIC Conditions of Contract for Construction 1999 (Red Book) and FIDIC Conditions of Contract for Plant and Design Build 1999 (Yellow Book) provides as follows:
“The Contractor shall be entitled subject to Sub-Clause 20.1 [Contractor’s Claims] to an extension of the Time for Completion if and to the extent that completion for the purposes of Sub-Clause 10.1 [Taking Over the Works and Sections] is or will be delayed by any of the following causes:
(d) Unforeseeable shortages in the availability of personnel or Goods caused by epidemic or governmental actions”
On its face, it would certainly appear appropriate to deem the embargo against the shipping of goods from the UAE to Qatar as a government action, however to be sure that it is applicable, there are a few items to consider more carefully.
Firstly, is there a shortage in the ‘availability’ of Goods? This is not immediately definitive, as the goods are available and it is only the fact that the delivery route to get them to Qatar is now much slower than originally planned. Although the meaning of ‘available’ is not defined, it would however be reasonable to argue that the goods would only be deemed to be ‘available’ when they are able to be in the possession of the Contractor. Although the goods are literally ‘available’ somewhere in the world, the fact that they cannot be utilized by the Contractor for the purpose of the works is arguably the intent of the clause. Either way, if the Contractor is going to suffer a delay by procuring the Goods from another source, or waiting for them to be delivered through an alternative route the Contractor is being prevented from utilizing the goods.
Secondly, we can consider if the actions of the UAE government were “Unforeseeable”, which is defined in the FIDIC suite as being “not reasonably foreseeable by an experienced contractor by the date for submission of the Tender”.
¹The Economist (Print edition – Middle East and Africa) reported on 19 October 2017, that prior to the diplomatic dispute, the port located in Jebel Ali of the UAE handled more than 85% of shipborne cargo destined for Qatar.
Although foreign policy experts may have been able to foresee such dispute, it appears that very few anticipated the types of prohibitions that have been levied. It could therefore only be reasonable to deem such knowledge or foresight to be well out of the realm of even an ‘experienced’ Contractor.
Finally, it is important to consider what was known at the ‘Tender Date’. Even if a tender is submitted after the commencement of the diplomatic dispute, the parties may have expected the matter to have been resolved quite quickly. It is safe to say that Contractors who did not account for these delays in tenders submitted after the commencement of the diplomatic dispute will have a more difficult case to make that such delays were ‘Unforeseeable’. However, this will depend greatly on the timing and specific circumstances of each case, and as a result, there may be a genuine case here for many Contractors who were delayed and denied an extension of time.
It is noted that the Conditions of Contract for EPC/Turnkey Projects 1999, (Silver Book) does not include an equivalent provision to clause 8.4(d) of the Yellow and Red Books. The Contractor therefore needs to look further into the terms to consider if any other sub-clause of the Silver Book gives the Contractor an entitlement to an extension of time.
Firstly, Contractors may expect clause 13.7 [Adjustment for Changes in Legislation] to provide some relief. However, this clause only relates to the “Laws of the Country”. Assuming the law of the country is Qatar then a change of laws in the UAE that prohibits a ship from travelling directly from the UAE to Qatar will not be relevant.
The Contractor may also consider Sub-Clause 17.4 [Consequences of Employer’s Risks]. However it is submitted that this sub-clause would likely fail on two key aspects. The diplomatic dispute does not directly fall within any of the items listed in 17.3. In addition, the delay of shipping goods would not amount to “loss or damage to the Works”.
Finally, the Contractor’s may look to the application of clause 19 [Force Majeure]². This may, on balance, be the Contractor’s best option. Unlike clause 8.4(d) of the Yellow and Red Books, Sub-Clause 19.1 does not include any direct reference to ‘government actions’. However, as the list of circumstances is ‘not limited’ to the items listed in 19.1(i)-(v), Force Majeure will apply if the Contractor can show that it was “prevented from performing any of his obligations under the Contract” by an exceptional circumstance that:
(a) was beyond the Contractor’s control;
(b) was unforeseeable³ before entering into the Contract;
(c) could not have been reasonably avoided or overcome; and
(d) is not attributable to either party.
This is a more difficult claim and has more hurdles to clear than clause 8.4(d) of the Yellow and Red Books. Each element noted above will need to be considered and addressed by the parties, particularly (b) where the critical date is the ‘date of the Contract’ rather than the ‘date of the Tender’, and (c) where the Contractor will need to justify why such goods could not be procured from another source who could deliver them directly to Qatar.
²This clause applies to the FIDIC Suite and is not only limited to the Silver Book.
³Note that this is not a reference to the term defined in the Contract.
If the scenario is deemed to be an event of Force Majeure then the Contractor will be entitled to an extension of time under clause 19.4(b) [Consequences of Force Majeure] (and by extension 8.4(b)) if:
(a) the Contractor has complied with Sub-Clause 19.2 [Notice of Force Majeure]; and
(b) the Contractor has suffered a delay as a consequence of the Force Majeure event.
In conclusion, there may be more than one way for Contractors impacted by the diplomatic dispute to claim an extension of time under FIDIC Contracts, or indeed contracts based on such principals and risk allocation. It is therefore important that these options are considered and analyzed as early as possible and all necessary notices are issued in accordance with the Contract in order to protect this entitlement to the extent possible. Failure to do so may limit the Contractor’s likelihood of success in obtaining such relief and consequently result in exposure to delay damages.
This article was written by Glenn Bull. For more information please contact Glenn on +974 6659 1654 or Glenn.Bull@crsblaw.com.
¹The Economist (Print edition – Middle East and Africa) reported on 19 October 2017, that prior to the diplomatic dispute, the port located in Jebel Ali of the UAE handled more than 85% of shipborne cargo destined for Qatar.
²This clause applies to the FIDIC Suite and is not only limited to the Silver Book.
³Note that this is not a reference to the term defined in the Contract.
Our thinking
Emma Humphreys
Property Patter: The last resort – FAQs on tenant liquidation
How does liquidation work?
Lee Medlock
Charles Russell Speechlys advises TDR Capital LLP and the Issa brothers on the real estate aspects of ASDA acquisition
TDR Capital LLP and the Issa brothers have completed their acquisition of a majority stake in ASDA from Walmart.
Lauren Fraser
Leasehold Reform – The devil is in the detail
Taking a closer look at the Government's announcement in January that makes home purchase easier and cheaper for leaseholders.
Lauren Fraser
Further extension to ban on residential evictions
There has been a further extension of the ban on enforcement of possession orders at residential dwellings in England until 31 March 2021 .
Carolyn Davies
Grand designs – Who should take the design risk in an MMC project?
MMC have been touted as a way to tackle costs and inefficiencies within construction, but who takes responsibility for the design ?
Emma Humphreys
Property Patter: Love Thy Neighbour - how to deal with boundary disputes
Boundary disputes often involve high levels of stress and costs.
Richard Flenley
A Cautionary Tale of a Brush Too Broad
Molly Tatchell
Definitions, definitions, definitions
David Savage
David Savage quoted by Construction Law on the confusion over construction contract liabilities arising from Covid-19
An increase in construction disputes relating to time and cost impacts of Covid-19 related project impacts has been seen.
Tom Davies
Government announces further funding for building safety
Laura Bushaway
Laura Bushaway writes for the Estates Gazette Legal Q&A on the implications of Covid-19 on business interruption policies
Laura Bushaway considers the question: Am I insured for Covid-19?
Helen Coward
New tax for UK Residential Developers
Helen Coward
Building anxieties: The impact of a possible CGT rate rise on housebuilders
As the March 2021 budget approaches and a potential CGT rate rise, what does it mean for housebuilders?
Fiona Edmond
Keeping Up With Construction: Pre-procurement - Practical Pointers
Successful procurement is more than the choice of the construction contract.
Emma Humphreys
Property Patter: The “bubble wrap” option – FAQs on tenant administration
The team look at some key points on tenant administration.
James Bateman
Draining Surface Water: Good news for Developers?
Helen Coward
Building anxieties: The impact of a possible CGT rate rise on housebuilders
Amy Shuttleworth
Urbanisation: a one way ticket to concrete jungles or the beginning of urban forests?
The sky is the limit...
David Haines
David Haines and Ingrid Saffin write for Caterer Licensee on the end of the rent moratorium
With the rent moratorium due to end on 31 March, David and Ingrid emphasise the importance of communication with landlords.
Claire Fallows
Claire Fallows writes for Planning Magazine on the proposed changes to permitted development rights to convert Class E to residential
According to government plans, certain properties will be able to convert to residential use without submission of a planning application.