Grand designs – Who should take the design risk in an MMC project?
Modern Methods of Construction (MMC) have been touted by many as a way to tackle costs and inefficiencies within the construction industry. The impacts of Brexit on worker availability, skills shortages in the construction industry, and the ever pressing need for affordable, high quality homes has meant that MMC may play an increasingly crucial role in the United Kingdom in future.
One of the issues to be considered on any MMC project is who is to take the responsibility for the design of the MMC elements? In traditionally built projects, there is generally a design phase and a construction phase. The developer’s professional team may retain responsibility for the bulk of the design of the works. Alternatively, the contractor may take responsibility for the design of the works under a design and build contract.
However, MMC introduces an additional element in this process, being the ‘manufacture’ step after design, and before construction on site. This manufacturing step may be undertaken by a specialist MMC contractor and may involve completing the design of elements of the MMC work.
The question of design risk on projects involving MMC is therefore not necessarily clear cut. There are a number of options that may be suitable depending on the type of project, the extent of the MMC required and the MMC capabilities of the parties involved.
Professional team retaining design responsibility
MMC may include completed rooms with internal and external finishes installed such as bathroom pods, hotel pods, or component parts of houses.
Developers can develop a comprehensive detailed design at an early stage for these modular elements in part due to the increased digitisation of construction design through tools such as BIM.
The advantages of the professional team taking on the design risk is that the developer’s design can be established and crystallised at an early stage, which can then be repeated over numerous different projects such as housing developments (although this will also depend on the copyright licences provided to the developer). There should therefore be limited unexpected costs arising on a project through design changes, one of the core benefits of MMC. As anyone watching Kevin McCloud over the years will know, the more changes to design that are made during development, the longer projects take and the more they cost.
In this scenario, a contractor would take responsibility for procuring the MMC elements in line with the professional team’s design, and then installing these MMC elements correctly on-site.
However, this approach relies on the professional team’s design being robust and the developer being comfortable with the main contractor not having single point design responsibility. If an element of the end works is defective due to design and installation issues, a developer would need to pursue both its professional team and the contractor, which will usually lead to longer and more expensive proceedings with arguments as to which party should take responsibility for the defects.
A developer could mitigate these issues by carrying out regular rigorous inspections of the works and maintaining thorough records, so that it can identify the responsible parties should defects arise.
Contractor taking single point design responsibility
Another option is for the contractor to have single point design responsibility on projects involving MMC elements.
A contractor may be comfortable accepting the design risk of MMC work to be designed by others. This will usually be subject to the contractor having recourse in respect of that MMC design through either novation of the relevant designer‘s appointment, or a collateral warranty provided by that designer. In addition, insofar as the MMC work is to be manufactured by a specialist MMC sub-contractor who is also taking design responsibility for some elements of the MMC work, that design risk could be accepted by a main contractor in a similar manner to the design risk of other elements of the works carried out by specialist sub-contractors.
Some main contractors and housebuilders have (or are increasing) their internal capabilities to manufacture elements of an MMC project. If the main contractor has the internal capability to design and manufacture elements of an MMC project, it would be able to accept single point responsibility for these elements and there would be no third party specialists from whom the main contractor had to secure contractual rights of recourse.
Insofar as the contractor is accepting the design risk for MMC work, its professional indemnity insurance would have to be carefully reviewed to ensure it adequately covers any design risk in MMC work.
Construction management
Some developers will procure their projects using construction management. In that situation there would be no main contractor. The developer would appoint the professional team and the trade contractors to design and construct the works, this would include the specialist MMC contractor.
The MMC contractor is only likely to accept single point design responsibility for the MMC work in such a situation if they have a contractual right of recourse against the members of the professional team who designed any parts of the MMC work. This cannot usually be provided by a novation of the relevant designer’s appointment, as their responsibilities would usually extend beyond the MMC work such that they would have to remain employed by the developer.
Such a contractual right of recourse could be provided by a collateral warranty from the relevant designers. However, if the relevant designers are not willing to provide such a collateral warranty, the MMC contractor is unlikely to accept single point design responsibility for the MMC work. The design responsibility for the MMC work would therefore be split between any party who had contributed to its design.
Conclusion
Parties are always considering design risks when considering procurement options and negotiating construction contracts. The introduction of MMC into a development is an added consideration in this process.
The key point is to ensure there is a clear agreement as to who is accepting the design risk for the MMC work and that this is properly documented in the various contracts for the construction of the project.
Carolyn Davies is an Associate in the Construction, Engineering and Projects team at Charles Russell Speechlys LLP. Carolyn can be contacted on +44 20 7438 2149 or by email: Carolyn.Davies@crsblaw.com.
Our thinking
Helen Coward
Some key takeaways from the draft legislation for Finance Bill 2022-23
In July 2022, the government published draft legislation ahead of potential inclusion in Finance Bill 2022-23.
Ilona Bateson
Top of the corporate agenda: modern slavery failings and mandatory supply chain disclosures
The Financial Reporting Council Lab has gone live with two new publications, signalling a market shift on supply chain issues.
Jonathan Steele
Charles Russell Speechlys advises the DiscoverIE Group on its acquisition of the CDT Group
The CDT Group, will be integrated with discoverIE's Contour business cluster within the Sensing & Connectivity division.
Naomi Nettleton
Charles Russell Speechlys advises Topland Group on new joint venture and £50m acquisition and financing of Allen House
Charles Russell Speechlys completes third major transaction with Topland Group this year
Piers Master
Bloomberg quotes Piers Master on the Zara family office
“Clients are increasingly mindful of the need to not to have all their eggs in one basket”
Steven Carey
Steven Carey and Carolyn Davies write for Construction News on a recent cladding court ruling
Cladding court ruling provides post-Grenfell liability pointers
Simon Green
Simon Green and Reem Al Mahroos write for Real Estate Asia on the trend of 'revenge tourism'
Revenge tourism is the new direction of travel for Asia...
Clare Davis
Clare Davis writes for Personnel Today on hot weather and employment law
Hot summers, hot desks – employment law advice on working through heatwaves
Hannah Turner
Q&A: Tackling technicalities and typos
Our experts answer a landlord’s query about the validity of a section 21 notice
Hope Barton
Q&A: The qualifying criteria explained
What do landlords need to prove to satisfy ground (g) of section 30(1) of the 1954 Act for the purposes of a new tenancy?
Michael Lingens
Charles Russell Speechlys has advised the owners of The Centre for Reproductive and Genetic Health (CRGH) on its sale to FutureLife
CRGH is the largest private fertility clinic in the London IVF market.
Naomi Heathcote
Green leases crucial to achieving net zero in the built environment
‘Net zero’ requires emissions to be reduced as far as possible, and for the remaining (or ‘residual’) emissions to be removed or captured.
Samuel Lear
Samuel Lear answers the EG Legal Q&A on code rights
Q&A: Code rights queries answered
Charlotte Duly
Retail Bulletin quotes Charlotte Duly on the House of Zana trademark row with Zara
"In this battle of David and Goliath, the little guy has come out on top."
David Coates
Charles Russell Speechlys advises Puma Private Equity on its investment into MUSO
We have advised long-term client Puma Private Equity on its investment into MUSO TNT Limited.
Helen Coward
FT Ignites Europe quotes Helen Coward on portfolio manager bonuses
"HMRC has had asset managers in their spotlight for some time now"
Melania Constable
Melania Constable and Jessica Williams write for Pharmacy Business on what the collapse of Testerworld means for community pharmacies
What does the collapse of Testerworld mean for community pharmacies?
Mark Howard
IT Pro quotes Mark Howard on investment in UK tech start-ups
"The UK has the strongest venture and growth capital funding ecosystem in Europe.”
Paula Boast
The impact of Bahrain’s new PPP Guide
Following on from the release of its Government Action Plan (2019-2022) Bahrain has now approved a guide regulating PPPs
James Broadhurst
Charles Russell Speechlys advises Gurr Johns on its acquisition of Forum Auctions Limited
Gurr Johns is one of the leading international, independent art advisory and appraisal firms.