The Gulf diplomatic dispute and construction claims - extensions of time
As Qatar continues its progresses towards the 2022 FIFA World Cup and the development strategy for the 2030 National Vision, the current diplomatic dispute occurring in the Gulf is impacting on many parties involved in construction projects occurring throughout the nation.
The question concerning many of these parties, whether consultants, contractors, sub-contractors, suppliers or employers, relates to claims and what relief, if any, the parties are entitled to under their respective contracts.
In this article, we will look at the Contractor’s right to an extension of time under the FIDIC suite of contracts where that extension of time has been caused by the late supply of goods being shipped to Qatar through the UAE.¹ Following the commencement of the diplomatic dispute, many Contractors have suffered delayed as a result of goods having to be shipped from the UAE to Oman before they could be transferred to a vessel that would deliver the goods onward to Qatar.
Clause 8.4(d) of the FIDIC Conditions of Contract for Construction 1999 (Red Book) and FIDIC Conditions of Contract for Plant and Design Build 1999 (Yellow Book) provides as follows:
The Contractor shall be entitled subject to Sub-Clause 20.1 [Contractor’s Claims] to an extension of the Time for Completion if and to the extent that completion for the purposes of Sub- Clause 10.1 [Taking Over the Works and Sections] is or will be delayed by any of the following causes:
(d) Unforeseeable shortages in the availability of personnel or Goods caused by epidemic or governmental actions”
On its face, it would certainly appear appropriate to deem the embargo against the shipping of goods from the UAE to Qatar as a government action, however to be sure that it is applicable, there are a few items to consider more carefully.
Firstly, is there a shortage in the ‘availability’ of Goods? This is not immediately definitive, as the goods are available and it is only the fact that the delivery route to get them to Qatar is now much slower than originally planned. Although the meaning of ‘available’ is not defined, it would however be reasonable to argue that the goods would only be deemed to be ‘available’ when they are able to be in the possession of the Contractor. Although the goods are literally ‘available’ somewhere in the world, the fact that they cannot be utilized by the Contractor for the purpose of the works is arguably the intent of the clause. Either way, if the Contractor is going to suffer a delay by procuring the Goods from another source, or waiting for them to be delivered through an alternative route the Contractor is being prevented from utilizing the goods.
Secondly, we can consider if the actions of the UAE government were “Unforeseeable”, which is defined in the FIDIC suite as being “not reasonably foreseeable by an experienced contractor by the date for submission of the Tender”.
Although foreign policy experts may have been able to foresee such dispute, it appears that very few anticipated the types of prohibitions that have been levied. It could therefore only be reasonable to deem such knowledge or foresight to be well out of the realm of even an ‘experienced’ Contractor.
Finally, it is important to consider what was known at the ‘Tender Date’. Even if a tender is submitted after the commencement of the diplomatic dispute, the parties may have expected the matter to have been resolved quite quickly.
It is safe to say that Contractors who did not account for these delays in tenders submitted after the commencement of the diplomatic dispute will have a more difficult case to make that such delays were ‘Unforeseeable’. However, this will depend greatly on the timing and specific circumstances of each case, and as a result, there may be a genuine case here for many Contractors who were delayed and denied an extension of time.
It is noted that the Conditions of Contract for EPC/Turnkey Projects 1999, (Silver Book) does not include an equivalent provision to clause 8.4(d) of the Yellow and Red Books. The Contractor therefore needs to look further into the terms to consider if any other sub-clause of the Silver Book gives the Contractor an entitlement to an extension of time.
Firstly, Contractors may expect clause 13.7 [Adjustment for Changes in Legislation] to provide some relief. However, this clause only relates to the “Laws of the Country”. Assuming the law of the country is Qatar then a change of laws in the UAE that prohibits a ship from travelling directly from the UAE to Qatar will not be relevant.
The Contractor may also consider Sub- Clause 17.4 [Consequences of Employer’s Risks]. However it is submitted that this sub-clause would likely fail on two key aspects. The diplomatic dispute does not directly fall within any of the items listed in 17.3. In addition, the delay of shipping goods would not amount to “loss or damage to the Works”.
Finally, the Contractor’s may look to the application of clause 19 [Force Majeure]². This may, on balance, be the Contractor’s best option. Unlike clause 8.4(d) of the Yellow and Red Books, Sub-Clause 19.1 does not include any direct reference to ‘government actions’. However, as the list of circumstances is ‘not limited’ to the items listed in 19.1(i)-(v), Force Majeure will apply if the Contractor can show that it was “prevented from performing any of his obligations under the Contract” by an exceptional circumstance that:
(a) was beyond the Contractor’s control;
(b) was unforeseeable³ before entering into the Contract;
(c) could not have been reasonably avoided or overcome; and
(d) is not attributable to either party.
This is a more difficult claim and has more hurdles to clear than clause 8.4(d) of the Yellow and Red Books. Each element noted above will need to be considered and addressed by the parties, particularly (b) where the critical date is the ‘date of the Contract’ rather than the ‘date of the Tender’, and (c) where the Contractor will need to justify why such goods could not be procured from another source who could deliver them directly to Qatar.
If the scenario is deemed to be an event of Force Majeure then the Contractor will be entitled to an extension of time under clause 19.4(b) [Consequences of Force Majeure] (and by extension 8.4(b)) if:
(a) the Contractor has complied Sub- Clause 19.2 [Notice of Force Majeure]
and
(b) the Contractor has suffered a delay as a consequence of the Force Majeure event.
In conclusion, there may be more than one way for Contractors impacted by the diplomatic dispute to claim an extension of time under FIDIC Contracts, or indeed contracts based on such principals and risk allocation. It is therefore important that these options are considered and analyzed as early as possible and all necessary notices are issued in accordance with the Contract in order to protect this entitlement to the extent possible. Failure to do so may limit the Contractor’s likelihood of success in obtaining such relief and consequently result in exposure to delay damages.
¹The Economist (Print edition – Middle East and Africa) reported on 19 October 2017, that prior to the diplomatic dispute, the port located in Jebel Ali of the UAE handled more than 85% of shipborne cargo destined for Qatar.
²This clause applies to the FIDIC Suite and is not only limited to the Silver Book.
³Note that this is not a reference to the term defined in the Contract.
This article was written by Glenn Bull. For more information please get in touch via glenn.bull@crsblaw.com or +971 4246 1909
Our thinking
Charity Training: Digital Transformation in the Charity Sector
We would be delighted if you could join us for the second session in our new series of bite-size webinars for charities.
Charity Training: Brand Protection
We would be delighted if you could join us for the first in our new series of bite-size webinars for charities.
Rose Carey
The UK’s New Skilled Worker & Intra-Company Visa Routes: a closer look
Taking a closer look at the UK’s new visas to assist UK businesses.
Carolyn Davies
Practicalities in Cladding Claims
Insight into Issues with Cladding Claims
Mark Rowden
EWS1 Forms - the latest episode
RICS have now published their highly anticipated guidance on when EWS1 forms will be required.
Laura Bushaway
Q&A: Am I insured for COVID-19?
Laura Bushaway writes for Estates Gazette on a recent claim under the “disease clause” of business interruption policy.
Simon Ridpath
The Purpose Podcast: Corporate purpose
Simon Ridpath discusses corporate purpose and the rise of environmental, social and governance (ESG) issues in “The Purpose Podcast”
Paul Henty
Client alert: Construction under competition law spotlight
We outline the three investigations which have either recently concluded or are ongoing together with what this means for businesses.
Emma Humphreys
Looking beyond the benefitted land: confirmation that an objector’s wider property may be considered in applications to discharge/modify restrictive covenants
Read our recent case study on applicants who were prevented from developing a new house due to a restrictive covenant covering their land.
Lauren Fraser
Further extension of coronavirus restrictions affecting residential properties: Where are we now?
The extension will be implemented from and including 31 March 2021 by the Coronavirus Act 2020.
Thomas Moran
Knight Frank Wealth Report: The Global Perspective on Prime Property & Investment
Knight Frank partners joined Charles Russell Speechlys for a virtual panel-led discussion on the Knight Frank Wealth Report
Daniel Moore
Case Study: One Blackfriars Limited
An informative and positive judgment for administrators selling high-value property in distressed and complex scenarios.
James Worthington
Keeping Up With Construction: Handover at Practical Completion - Practical Pointers
Practical tips for the handover of a successful project.
Paul Arathoon
Charles Russell Speechlys advises on Trident Royalties’ US$28m Placing
Trident Royalties plc is a growth-focused mining royalty and streaming company.
Jessica Williams
Temporary restrictions on winding-up petitions extended until 30 June 2021
As the restrictions are extended, read what it means for you here.
Steven Carey
Steven Carey writes for Building on whether a company can provide expert services in claims for and against the same party
A recent appeal case looked at whether a company can provide expert services in claims for and against the same party.
Adrian Mayer
InvestAfrica: Checking in or Checking out? Financing Africa’s Hotels in 2021
The discussion examined the strategies investors and financial institutions can implement to mitigate the effects of the pandemic.
Paul Arathoon
Charles Russell Speechlys advises Avation plc on £7.5m secondary placing
Headquartered in Singapore, Avation plc manages a fleet of aircraft which it leases to airlines across the world.
Sara Wilson
Sleep-in workers not entitled to NMW for entire shift
A unanimous ruling by The Supreme Court in the Royal Mencap v Tomlinson-Blake and another case.
James Souter
Q&A: Parking privileges
James Souter and David Nicholls address a resident’s parking dilemma.