Multi-tiered Dispute Resolution Clauses
It is perhaps an obvious statement but the larger or more complex the construction project, the more potential exists for things to go wrong and for more disputes to arise during the course of the project.
Traditionally arbitration has been favoured on major projects due to its perceived flexible procedural approach, neutrality, expertise of the arbitrators, time and cost effectiveness compared to court proceedings and confidentiality. Another factor in the international context, is the cross border enforcement of arbitral awards through the Convention on the Recognition and Enforcement of Foreign Arbitral Awards 1958 (“The New York Convention”), where the contracting parties may not be based in the same country or indeed in the same country as the construction project.
However, most of these perceived advantages do not stand up to scrutiny. Whilst many of the procedural requirements of legal proceedings have been incorporated into many institutional arbitration rules (for understandable reasons), this has led to arbitrations potentially taking just as long to conclude as legal proceedings and incurring the same levels of costs (if not more if there are three arbitrators). Again, from an international context, the importance of enforceability has diminished, certainly within the European Union and where the arbitrating parties are subject to bilateral trading arrangements.
A further factor is that if disputes arise during the course of the project, requiring the parties to arbitrate or litigate those disputes during the course of the project may seriously affect the commercial relationship between the parties and may greatly disrupt the performance of the contract.
Whilst most construction projects in the UK have the benefit of statutory adjudication (a form of interim binding alternative dispute resolution), certain types of projects in the UK and certainly many international projects will not.
These factors have led to an increasing prevalence of multi-tiered dispute resolution clauses (“MTDRCs”) within the contract. Such clauses provide a number of stages of alternative dispute resolution procedures with legal or arbitration proceedings being the process of last resort.
There are many forms of MTDRC, setting out various requirements, but typically consist of:
- A requirement of senior employees of each party to meet to try to resolve the dispute;
- If the dispute is not resolved by senior employees it is referred to a third party to give an interim decision on the dispute, such as adjudication or expert determination.
- If either party is dissatisfied with the interim decision, they can commence legal or arbitration proceedings.
Although many standard forms of contract now contain MTDRCs (e.g. NEC4, FIDIC, World Bank standard forms) and many dispute resolution institutions provide suggested wording for MTDRCs, care must taken when drafting such clauses to ensure they are enforceable. This is particularly the case where there the clause purportedly obliges the parties representatives to meet and negotiate a resolution.
A failure to follow the correct procedure could mean that an arbitration commenced without complying with prior MTDRC steps would result in an unenforceable arbitral decision. The worst case scenario would be where there are time bars or limitation issues which could mean a party losing its right to ultimately litigate / arbitrate the dispute.
With that in mind, and whatever the governing law of your contracts any dispute resolution procedure benefits from clear and precise rules that are readily understandable and may well avoid disputes about the dispute resolution procedure.
Drafting Points to Consider:
- Use Mandatory not permissive language (“the parties shall”, not “the parties may”)
- Avoid using terms such as “good faith”, “friendly negotiations”, “best endeavours”.
- Do not leave matters or steps “to be agreed”.
- Define the process precisely. Clearly set out how each step in the MTDRC is commenced and how it is to be conducted. For example, if there is a dispute resolution board, ensure parties agree on a defined set of specific rules (e.g. International Chamber of Commerce Dispute Rules Board).
- Give each step a time limit. This allows each party to know how long the process will take, avoids open ended rounds of negotiations and ensures the parties have clarity on potential limitation / time bar issues.
- Specify the consequences of a failure to comply with a prior step. For example, “the parties may not commence arbitration without first having the matter decided by Adjudication on an interim basis.” A failure to specify any consequences may give immediately preceding steps little force and render those steps unenforceable.
This article was written by Michael O'Connor. For more information please contact Michael on +44 (0)20 7427 6441 or michael.o'connor@crsblaw.com
Our thinking
IBA Annual Conference
The IBA heads to Miami for its 2022 Annual Conference bringing together thousands hundreds of lawyers from around the world.
Martin Wright
Joint Venture Opportunities
Join our panel where we will discuss various topics including Joint Venture structuring and Partner procurement.
Sarah Anticoni
FT Wealth quotes Sarah Anticoni on forum shopping
"Being the first to file for divorce is not a foolproof way of securing an English hearing"
Louise Ward
What can UK investors interested in Life Sciences learn from their more experienced, including US, counterparts?
The recent tie-up between Canary Wharf and Kadans demonstrates the enthusiasm to access the lucrative UK life sciences market.
Helen Coward
Helen Coward writes for Tax Journal on the main purpose test for SDLT group relief
Mainly ignored? The main purpose test for SDLT group relief
Patricia Nathan-Amissah
The Ayes have it - Collateral Warranties can be a ‘Construction Contract’
The Court of Appeal handed down its judgment in the case of Abbey Healthcare (Mill Hill) Limited v Simply Construct (UK) LLP
Jonathan Morley
Charles Russell Speechlys advising Battery Ventures on the sale of SPT Labtech for £650 million.
Battery Ventures has raised over $9 billion to invest in software and services, enterprise infrastructure, and much more around the world.
Sarah Farrelly
Windrush Day 2022 – supporting access to justice
Charles Russell Speechlys is proud to continue supporting survivors of the Windrush scandal in their fight for justice.
Laura Bushaway
The Leasehold Reform (Ground Rent) Act 2022: Landlords and developers beware serious sanctions for non-compliance
The Leasehold Reform (Ground Rent) Act 2022 received Royal Assent on 8 February 2022 and will come into force on 30 June 2022.
David Coates
Charles Russell Speechlys has advised long-standing client Stonegate on a series A investment into Peckwater Brands
Stonegate is one of the largest pub companies in the UK with a rich portfolio that covers over 4,500 sites.
Sarah Farrelly
Pro bono support for major office premises move for charity in Stoke-on-Trent
Emmaus entities provide safe homes, community support and meaningful work to formerly homeless people across the UK.
Rachel Warren
Financier Worldwide quotes Rachel Warren on the UK’s Economic Crime Act
Evaluating the UK’s Economic Crime Act
Samuel Lear
Property Patter: Reasonable Endeavours
What does it mean to use ‘best’, ‘all’ or ‘reasonable’ endeavours?
Glenn Bull
The balance between Fairness and Certainty in UAE Construction Contracts
Articles 106 and 390(20) arguably make the UAE more focused on fairness than some of its counterparts in the GCC.
Rose Carey
Could the UK’s Life Sciences Vision be restricted by its Immigration Policy?
We explore some of the visa options that may be open to businesses in the sector and their relative pros and cons.
Joshua Green
Joshua Green writes for Spear's Magazine on Wagatha Christie’s lessons for HNWs
Wagatha Christie’s lessons for HNWs
Stephanie Bonnello
Stephanie Bonnello writes for the Practical Law Dispute Resolution blog on witness evidence
When are witness summaries permitted instead of witness statements and when should material be struck out from a witness statement?
Emma Humphreys
Emma Humphreys and Paul McCarthy write for Property Week on the new landlord digital ID checks
Emma Humphreys and Paul McCarthy write for Property Week on new landlord digital ID checks
Carolyn Davies
Carolyn Davies and Oliver Park write for Property Week on the key property points in the Building Safety Act
The key property points in the Building Safety Act
Oliver Auld
Unexplained Wealth Orders & Trustees
Learn about Unexplained Wealth Orders, what they are, who can obtain them and the implications that exist for trustees.