Hacking through the JCT Payment Mechanism and Adjudication?
In the leading judgment in the Court of Appeal’s decision in Grove Developments v S&T dealing with “smash and grab” adjudications, Sir Rupert Jackson observed:
“We are all trying to hack out a pathway through a dense thicket of amended legislation, burgeoning case law and ever-changing standard form contracts”.
But having hacked through this thicket, has Sir Rupert cleared the pathway only to find another thicket for the JCT interim payment mechanism?
A reminder of the facts
Grove engaged S&T under a JCT Design and Build Contract 2011 (with certain amendments). Near the end of the works, an interim payment dispute arose and S&T commenced an Adjudication seeking payment of the applied for sum of c£14M. S&T argued Grove had failed to issue a valid payless notice and therefore the sum applied for had become the certified sum and payable.
Grove argued that it had served a valid payless notice – the first adjudicator decided it had not - but also commenced a second adjudication seeking a “true valuation” of the interim account.
Grove refused to pay the £14M and sought declarations from the High Court that its payless notice was valid and that it could commence a second adjudication on the “true value” in any event.
Coulson J decided the payless notice was valid and therefore there was no obligation to pay the £14M. Coulson J also went on to decide that even if there was no valid payless notice, Grove had the right under the Contract and the Housing Grants Construction and Regeneration Act 1996 as amended (the Act) to commence the second “true value” adjudication.
The Court of Appeal’s Decision
The Court of Appeal expressly endorsed Coulson J’s decision, confirming:
- Interim ‘certified sums’ were provisional and not conclusive as to the “true value” of work done;
- An adjudicator, arbitrator, judge has wide powers to open up any certified sums where those sums are disputed.
- An employer could commence a second “true value” adjudication
- An employer may recover “any overpayment” made at an interim stage and the adjudicator must be able to “…give effect to the financial consequences of his decision.”
- The Act and the contract prohibit an employer from embarking on the “true value” adjudication before he has complied with the obligation to make payment.
Analysis / Comment
Whilst the implications of this case will still need to be worked through – including whether the judgment brings about the end of smash and grab adjudications – (my view is that it will not), the judgment arguably creates a potential conflict with the Act and interim payment mechanism of JCT contracts.
Under JCT interim payment mechanisms (unlike the NEC suite of contracts) there is no right or obligation on the Contractor to make an interim / balancing payment to the Employer where there is a negative interim certificate.
Where there had been previous overvaluations, the normal course is for the certificate to certify the negative sum and state there was a “nil” balance due that month. The expectation was there would then be an adjustment in later certificates.
Although the Court of Appeal was not concerned with the recovery of potential historic overpayments (Grove acknowledged that c£276,000 was due to S&T), in deciding that an employer can recover “any overpayment” and that the adjudicator has the power to give effect to the financial consequences of his decision, it is arguable that the Court of Appeal’s decision does give employers a right of repayment for historic over certification and not just the overpayment arising from the failure to issue a payment or payless notice.
Whilst Sir Rupert Jackson acknowledged that there was no express provision under the JCT wording permitting negative interim payments, he noted that s111 of the Act (the obligation to pay the certified sum) applied to both interim and final payments. Section 111 of the Act refers to “payers” and “payees” of interim and final payments and therefore a contractor could be a “payer” at both interim and final payment stages.
He further noted that the Court of Appeal had determined in the case of Harding v Paice that an employer has the right to challenge the notified final payment (where he had failed to issue a payment or payless notice) commenting “…it would be strange if that same form of words [under section 111] has a conclusive effect in relation to interim certificates which it does not have in relation to final certificates…” and affirming the analysis that “If an adjudicator finds that the employer has overpaid at an interim stage, he can order re-payment of the excess…”
This analysis does appear to create a tension between the express wording (and agreement of the parties) under a JCT contract and the interpretation of payment obligations under the Act. Perhaps more importantly it runs the risk of counteracting the Act’s widely acknowledged policy of promoting cashflow, although users of NEC suite of contracts will be well accustomed to this scenario.
It will be interesting to see how the courts and adjudicators, as well as the JCT drafting committee, hack away at this thicket in the future.
Our thinking
Martin Wright
Joint Venture Opportunities
Join our panel where we will discuss various topics including Joint Venture structuring and Partner procurement.
Rupa Lakha
Construction & Infrastructure Seminar
Join our experts who will give insights and analysis on the latest sector updates.
Patricia Nathan-Amissah
The Ayes have it - Collateral Warranties can be a ‘Construction Contract’
The Court of Appeal handed down its judgment in the case of Abbey Healthcare (Mill Hill) Limited v Simply Construct (UK) LLP
Glenn Bull
The balance between Fairness and Certainty in UAE Construction Contracts
Articles 106 and 390(20) arguably make the UAE more focused on fairness than some of its counterparts in the GCC.
Carolyn Davies
Carolyn Davies and Oliver Park write for Property Week on the key property points in the Building Safety Act
The key property points in the Building Safety Act
Carolyn Davies
Carolyn Davies writes for Construction News on stakeholders new duties under the Building Safety Act
“The act brings some of the most significant changes to the construction industry in years”
Steven Carey
Steven Carey writes for Building Magazine on the new Building Safety Act and the associated changes
Steven Carey writes for Building Magazine on the Building Safety Act
David Savage
David Savage writes for PBC Today on the end of rebated fuel
David Savage writes for PBC Today on the end of rebated fuel
David Savage
David Savage quoted in Building Magazine on construction red diesel usage
David Savage comments in Building Magazine on the use of red diesel in the construction industry
Fiona Edmond
Fiona Edmond quoted in Building Magazine on the potential legal impact to contractors
Fiona Edmond quoted in Building Magazine on the potential legal implications to contractors
Michael O'Connor
Explain the rules for disclosure of documents
Michael and Octavia explore the case of Provimi France SAS and others v Stour Bay Company Ltd.
Jane Burrows
Jane Burrows writes for Building on when defects could prevent practical completion
Jane Burrows explains when a defect could prevent practical completion as opposed to just being a snagging item.
Fiona Edmond
Charles Russell Speechlys advises Derwent London on £158m building contract with Laing O’Rourke
Derwent London is a British-based property investment and development business.
David Savage
David Savage quoted by The Construction Index on the implications of the proposed The Carbon Emissions (Buildings) Bill
The bill requiring the whole-life carbon emissions of buildings to be reported has started its passage through the legislative system.
Mazin Al Mardhi
Mazin Al Mardhi and Dana Marshad write for The Construction Disputes Law Review on developments to construction law in Bahrain
Mazin and Dana provide an update on the latest developments to construction law in Bahrain,
Naomi Nettleton
Charles Russell Speechlys advises Topland Group on two key transactions
Topland Group is one of the largest multi-billion pound, privately owned investment groups.
Sam Johnson
Expert Shopping – Seeking to rely on a new expert
A practice known as expert shopping may see the court order the disclosure of the previous experts.
Fiona Edmond
Charles Russell Speechlys advises Derwent on Francis House letting to Edelman
The firm advises long-standing client Derwent London plc on the letting of Francis House in London to global communications firm Edelman.
Chi Mount
Chi Mount writes for Building on the differences between a reasonable skill and care obligation and a fitness for purpose obligation
Chi explains the differences between a reasonable skill and care obligation and a fitness for purpose obligation.
James Worthington
James Worthington quoted by Construction Law on the Private Member’s Bill proposing to abolish cash retentions within construction contracts
A Private Member’s Bill proposing to abolish cash retentions within construction contracts has had its first reading in the House of Lords.