Don’t delay in documenting your disruption: court considers IT sourcing disputes and relief notices
The Court of Session in Edinburgh recently considered a dispute between an IT contractor supplying services to the Edinburgh City Council and its sub-contractor. The judgement highlights some interesting take-homes about the importance of documenting any delays in the provision of services by a supplier, along with the underlying cause of the delay. Good contractual governance mechanisms may also be helpful here.
In a preliminary hearing the Court considered arguments relating to the causes of the IT project delays and whether the sub-contractor (Agilisys Limited) was entitled to relief from delay under relevant relief notices. Agilisys was engaged by contractor CGI IT UK Limited (CGI) to perform a sub-contract as part of the council’s digital transformation programme.
CGI blamed Agilisys for the delays, however Agilisys terminated the sub-contract and claimed damages, because of what it considered to be CGI's repudiatory breaches of the sub-contract.
The Court criticised the arguments put forward by CGI about the cause for the delays noting that "contemporaneous documentation" was "the best evidence" to assess whether the delays lay with Agilisys. CGI failed to provide any evidence of this kind to support its claims, instead relying on retrospective testimonies from witnesses.
The judge noted that “the position put forward by CGI witnesses in the course of the proof was: there were a significant number of very serious, longstanding and repeated failures by Agilisys to meet their obligations in terms of the sub-contract. […] If CGI were genuinely being hampered by failures on the part of Agilisys to fulfil its obligations I would have expected to see a consistent picture of such issues being raised with Agilisys in the contemporaneous documentation. I believe that is particularly so given the very serious effect which CGI said these failures were having on the implementation of the two projects.”
CGI argued that its lack of contemporaneous evidence could be explained by the partnership approach it said it followed in working with Agilisys, because it did not "attribute and document fault", and because it was "interested in moving ahead with the contract".
In looking at the circumstances surrounding the relief notices Lord Bannatyne concluded that CGI had breached its obligations to Agilisys under the sub-contract, and that there had been no breach or contribution to the breach by Agilisys. Lord Bannatyne also found that the breaches by CGI caused, or were reasonably likely to cause Agilisys to fail to achieve the milestone dates set out in the project implementation plan by the relevant completion date.
Comment: The judgement highlights the importance of maintaining a full paper trail where the provision of services by a supplier are falling behind schedule. Always document reasons for the delay (do not delay preparation of documentation - contemporaneous notes are valuable and the best evidence in any later claim).
This also highlights the benefits of ensuring that any material services contracts of this nature include robust governance and escalation procedures to ensure that any delays are reported to relevant individuals of the right seniority, both on the customer and supplier side. The parties should also consider formal contractual processes for the issuance of remediation or warning notices if service levels or timescales are not met.
The Court will consider whether Agilisys was entitled to terminate the contract at a later date.
For more information please contact Christina Fleming on +44 (0)20 7427 1022 or at christina.fleming@crsblaw.com.
Our thinking
Michael Lingens
Charles Russell Speechlys has advised the owners of The Centre for Reproductive and Genetic Health (CRGH) on its sale to FutureLife
CRGH is the largest private fertility clinic in the London IVF market.
Naomi Heathcote
Green leases crucial to achieving net zero in the built environment
‘Net zero’ requires emissions to be reduced as far as possible, and for the remaining (or ‘residual’) emissions to be removed or captured.
Samuel Lear
Samuel Lear answers the EG Legal Q&A on code rights
Q&A: Code rights queries answered
Charlotte Duly
Retail Bulletin quotes Charlotte Duly on the House of Zana trademark row with Zara
"In this battle of David and Goliath, the little guy has come out on top."
David Coates
Charles Russell Speechlys advises Puma Private Equity on its investment into MUSO
We have advised long-term client Puma Private Equity on its investment into MUSO TNT Limited.
Helen Coward
FT Ignites Europe quotes Helen Coward on portfolio manager bonuses
"HMRC has had asset managers in their spotlight for some time now"
Melania Constable
Melania Constable and Jessica Williams write for Pharmacy Business on what the collapse of Testerworld means for community pharmacies
What does the collapse of Testerworld mean for community pharmacies?
Mark Howard
IT Pro quotes Mark Howard on investment in UK tech start-ups
"The UK has the strongest venture and growth capital funding ecosystem in Europe.”
Christopher Hadnutt
Chris Hadnutt writes for Building Magazine on construction project defects
Chris Hadnutt writes for Building Magazine on construction project defects
Tristram van Lawick
The Sunday Times quotes Tristram van Lawick on investment into country estates
“For overseas buyers the security of the UK property market is seen as a safe investment compared with other parts of the world"
Nicola Saccardo
Charles Russell Speechlys welcomes Partner Nicola Saccardo to the Firm’s London office
Charles Russell Speechlys welcomes Partner Nicola Saccardo
Simon Ridpath
Charles Russell Speechlys announces 24% international revenue growth
Charles Russell Speechlys announces 24% international revenue growth
Michael Powner
Barrister with gender critical beliefs discriminated against by chambers
An employment tribunal has found that the barrister, Allison Bailey was discriminated against because of her gender critical beliefs.
Chris Haywood
Chris Haywood writes for The Oath on the impact of Dubai's new Virtual Asset Law on NFTs and the metaverse
A future-ready framework?
Sarah Morley
The new UK register of overseas entities – the impact on property transactions
The Economic Crime Act establishes a new register of beneficial ownership of overseas entities, read the implications here.
Piers Master
Register of Overseas Entities: What are the deadlines for trust structures holding UK real estate?
The ROE is intended to launch on 1 August 2022 - read more about the deadlines trust structures holding UK real estate will be facing
Emma Preece
EG quotes Emma Preece on the Cine-UK and Cineworld Court of Appeal Covid rent arrears ruling
“This appeal was always going to be an uphill battle for the tenants.”
David Savage
Construction News quotes David Savage on a recent fire safety ruling and the implications of this
"Although clearly fact-specific as any case is, this is an interesting and important case..."
Sally Ashford
Changing an Enduring Power of Attorney
Learn what you need to know about changing an Enduring Power of Attorney to a Lasting Power of Attorney.
Rhys Novak
Charles Russell Speechlys helps defeat bribery prosecution in stunning victory in the Milan Court of Appeal
Charles Russell Speechlys victorious in the Milan Court of Appeal