Steven Carey and Carolyn Davies write for Construction News on a recent cladding court ruling

min read

The case of Martlet Homes Limited v Mullaley and Co Limited is the first post-Grenfell Technology & Construction Court decision on a claim relating to fire safety and cladding. While the court went out of its way to emphasise that this case was fact-specific, everyone concerned with cladding claims will pore over this decision.

Steven Carey, Partner, and Carolyn Davies, Associate, write for Construction News on the decision. Read their article below:

"One of the key take-home elements from this case is that the defence of ‘everyone else was doing it’ seems to be given short shrift"

Social housing provider Martlet owns five tower blocks in Gosport, Hampshire, all taller than 18 metres. In the early 2000s, the previous owner engaged Mulalley to undertake refurbishment work, which was completed in 2008. This included the application of external wall insulation (EWI) to most elevations to improve thermal performance.

No particular problems were observed in the cladding system following practical completion. However, after the Grenfell fire, Martlet undertook urgent investigations, after which it decided to replace the towers’ cladding and maintain a ‘waking watch’ until remedial works were complete.

Martlet claimed the resulting costs from the contractor on the basis that there had been (a) a breach of the specification and (b) a failure to install the EWI system using proper workmanship.

Breach of regulations

The specification had expressly required the contractor to comply with BR 135, which introduced a fire-performance standard for external thermal insulation on multistorey buildings. The court said that, given the nature of the works, any reasonably competent designer at the time ought to have had regard to BR 135 and enquired whether the EWI system met the functional requirements in the building regulations. It found that the contractor was plainly in breach of this obligation.

The court noted that this logic applied irrespective of whether there was an express contractual obligation to comply with BR 135, and whether everyone else was doing it at the time.

The court rejected the contractor’s reliance on a vaguely worded 1995 BBA certificate on the EWI as evidence that it complied with building regulations. While such product certificates can be used as one of the many tools in assessing compliance, they are not definitive evidence.

Mulalley also argued that Martlet’s remedial actions were due to guidance issued post-Grenfell rather than the contractor’s works. However, the court held that the contractor’s breach of the specification was an effective cause of the remedial works and therefore Martlet was entitled to recover the cost of these works (with some adjustment).

If Martlet had been able to demonstrate that the contractor was liable only for the poor standard of the installation (rather than also being liable for the defective design), Martlet’s recovery from the contractor would have been limited to the cost of a repair scheme only, rather than for the full replacement costs and a waking-watch scheme.

Remediation options vary

The practical implication is that if there was an EWI system with installation defects, this does not automatically mean the entire system must be replaced if a more limited remedial scheme could remedy the relevant defects.

The introduction of PAS 9980 in January provides a baseline methodology to inform appraisals of remedial work to external walls. We may see more cases in future that consider different remediation options, based on this code of practice.

One of the key take-home elements from this case is that, in the context of exercising reasonable skill and care, the defence of ‘everyone else was doing it’ seems to be given short shrift. The court will not exonerate a party that simply proves that others were just as negligent.

It is also plain that the construction industry needs to focus on improving competence and keep up with the requirements introduced by the Building Safety Act 2022 and the new Building Safety Regulator.

Read the full article first published in Construction News (subscription required).

Our thinking

  • IBA Annual Conference 2026

    Jean-Baptiste Beauvoir-Planson

    Events

  • 9fin quotes Jamie Rhodes and Tom Smitham on the growing role of private capital in football finance

    Jamie Rhodes

    In the Press

    min read
  • EU Packaging and Packaging Waste Regulation: Who Is Affected?

    Kerry Stares

    Quick Reads

    min read
  • The National Security and Investment Act, Five Years On: What the 2025-26 Annual Report Tells Foreign Buyers

    Greg Stonefield

    Insights

    min read
  • EU Packaging and Packaging Waste Regulation: Three Things You Need to Know

    Kerry Stares

    Quick Reads

    min read
  • Jersey Trade Mark Reform: What the New Regime Means for You

    Dewdney William Drew

    Quick Reads

    min read
  • The Telegraph quotes Julia Cox on the growing use of Family Investment Companies for inheritance planning

    Julia Cox

    In the Press

    min read
  • Tessa Bartley comments in Legal Futures about our framework for choosing the right legal AI tools

    Tessa Bartley

    In the Press

    min read
  • Investors’ Chronicle quotes Katie Talbot on the risks and responsibilities of undertaking a trustee position

    Katie Talbot

    In the Press

    min read
  • Chiara Muston comments in Employee Benefits on minimum wage enforcement changes

    Chiara Muston

    In the Press

    min read
  • Retail Collection: Reputation management for brand founders

    Claudine Morgan

    Podcasts

  • Charlie Ring and Mike Barrington write for Professional Adviser on how best to prepare for the sale of a financial services business

    Charlie Ring

    In the Press

    min read
  • EU Packaging and Packaging Waste Regulation (PPWR)

    Kerry Stares

    Insights

    min read
  • Beware the “late invoice” clause: TCC confirms the final date for payment must be fixed to the due date

    William Turner

    Insights

    min read
  • Fraudsters in the Inbox: The Limits of Contractual Causation in Logix Aero v Siam Aero

    Natalya Stone

    Insights

    min read
  • Light Bites, expert nuggets for the seasoned developer: bonus episode

    James Souter

    Podcasts

  • Mace Construct Ltd v Baltic Investment Holdings Ltd: A case highlighting the risk of including tender clarifications and schedules of derogations in building contracts

    Henry Dalton

    Insights

    min read
  • Child Maintenance: Reform, a Key Appeal, and the Elusive Christmas Order

    David Carver

    Quick Reads

    min read
  • High Court interprets repair covenant in Hotel lease and statutory fire safety obligations

    Chandni Pandya

    Insights

    min read
  • Be Careful What You Wish For: In the UAE, How a Tenant’s Force Majeure Claim Can Dissolve Its Own Lease

    Glenn Bull

    Insights

    min read
Back to top