• news-banner

    Expert Insights

Q&A: Terminating a contract – matters of materiality

min read

Question

I am buying an off-plan house from a developer. The contract contains a provision that says the developer won’t make changes that will “materially affect the size, layout, or appearance of the rooms”. I have now been told that the layout and size of the master bedroom will be very different to the plan. The room is going to be 10% smaller and I am also not happy with the changed layout. The developer has confirmed practical completion is imminent. Can I terminate the contract?

Answer

It is going to depend on both the wording of your contract and the circumstances of the case. Without a bit more detail on either of those, we cannot give a definitive answer. The first step would be to check the contract to see whether: (i) it defines what a “material change” on the size, layout, etc is; and (ii) whether it provides that any material change in size, layout, etc is also a material breach allowing you to terminate the contract. Although both use the term “material”, these two issues are different. It is only if a breach of the contract is material that it might allow you to terminate it.

Explanation

If either or both of “material change” and “material breach” are not defined, then in order to assess whether or not (i) the change is material and (ii) it is likely to amount to a material breach, you have to look at all the circumstances of the case. For example, if you’ve bought a 12-bedroom mansion with a master bedroom bigger than most flats, a 10% reduction may not be either a material change or, even if it is, may not be a material breach. If it is a small one-bedroom house and that reduction takes it below nationally required space standards, it might be different. As questions like this are fact and contract dependent, we suggest that you seek legal advice.

A similar situation to this was considered by the Court of Appeal in Mears v Costplan Services (South East) Ltd and others [2019] EWCA Civ 502; [2019] EGLR 22, which concerned the construction and lease of two blocks of student accommodation. The landlord wanted to get substantial building works done and then lease out the blocks. It entered into an agreement for lease (AFL) with Mears, under which the landlord agreed to carry out the “Landlord’s Works” (ie building works) and that five days after practical completion it would grant Mears (and Mears would execute) a lease. The “Landlord’s Works” were defined to include key components of the construction contract between the landlord and its builder. The AFL also included a provision that the landlord would not vary the Landlord’s Works or Building Documents so as to “[m]aterially affect the size (and a reduction of more than 3% of the size of any distinct area… shall be deemed material), layout or appearance of the Property”. As built, there were 56 failures to meet that 3% tolerance. Mears argued that, on a true construction of the AFL, any failure to meet the 3% tolerance was a material and substantial breach, permitting the termination of the AFL.

The Court of Appeal disagreed. It held that while it was open to the parties to agree, in advance, that a breach of a particular clause is a “material” or “substantial” breach of contract allowing it to be terminated, this had to be set out in clear terms. Looking at the wording of the clause and the commercial context, this is not what the clause did. Instead, the wording was fairly clear in that the clause identified what would be a “material” reduction in room size (enough to constitute a breach of contract), but not whether that breach would be material. This made sense in the construction context, where there may be all sorts of reasons why a room might be built smaller than in the drawings, and the extent of any departure might be very modest. It would have been commercially unworkable if say, one 3% reduction would have allowed Mears to determine the AFL. Therefore, although failing to meet that 3% threshold was a material change on size (and so a breach) and although there were therefore 56 breaches of the contract, whether those breaches were enough (individually or together) to constitute a material breach of the contract was a matter of fact and degree.

Against that background, we would really need to look at the whole contract and the context in order to properly advise you. The discrepancy here (10%) is obviously bigger than the one in Mears, both overall, and (given that you’re buying a house not blocks of flats) in relation to what you’re buying. But, the extract you have given us does not define what is a “material change”, nor does it say that would be a material breach. Therefore, we would suggest that you consult a lawyer.

This article was first published in Estates Gazette on 15 December 2020 and was published by Associate, Megan Davies and barrister, Nicholas Grant at Landmark Chambers.

Our thinking

  • IBA Annual Conference 2026

    Jean-Baptiste Beauvoir-Planson

    Events

  • Surveyors' Refresher Seminar

    Hope Barton

    Events

    min read
  • What Wadworth Tells Us About the Next Phase of PISCES

    Greg Stonefield

    Insights

    min read
  • Supply chain: social audits

    Kerry Stares

    Insights

    min read
  • Summer 2026 Update: Where are we are on the Government’s roadmap to Commonhold?

    Laura Bushaway

    Quick Reads

    min read
  • Leasehold and Freehold Reform Act 2024: New consultations on valuation and legal costs of enfranchisement and lease extension claims

    Laura Bushaway

    Quick Reads

    min read
  • Leasehold Reform; Government responds to consultation on service charge regulation

    Laura Bushaway

    Quick Reads

    min read
  • Building Safety Levy: What Do the Proposed 2026 Amendments Mean?

    Mark Barley

    Insights

    min read
  • Autumn Budget 2026: possible CGT changes and pre-budget planning

    Julia Cox

    Insights

    min read
  • Family team successfully represent high-profile businessman in High Court jurisdiction dispute case

    Matt Foster

    Quick Reads

    min read
  • Can you terminate an “indefinite” trade mark licence even if there’s no express right to do so?

    Isabella Ross-Skinner

    Insights

    min read
  • Shaping the Future of AIM: What the New AIM Rules Mean for Growth Companies, Founders and Advisers

    Paul Arathoon

    Insights

    min read
  • Charles Russell Speechlys named a ‘Firm to Watch’ by India Business Law Journal

    News

    min read
  • Kerry Stares, Rory Partridge, and Lyla Gilbert write in Packaging Europe about landmark reforms on packaging sustainability regulations in the UK and Europe

    Kerry Stares

    In the Press

    min read
  • Rebecca Morjaria and Steven Carey write in Building about liability for defective construction products

    Rebecca Morjaria

    In the Press

    min read
  • Arbitrating Construction Disputes – Comparing the ICC, LCIA, SIAC and SCCA Rules

    Christopher O'Brien

    Insights

    min read
  • Simon Ridpath discusses Charles Russell Speechlys' strategic US expansion with Legal Business

    In the Press

    min read
  • What last week’s Bank of England decision means for private capital stakeholders

    Philip Withey

    Insights

    min read
  • Corporate Deal Highlights - A spotlight on H1 2026

    Sarah Wigington

    Insights

    min read
  • Anna Sowerby writes in City AM about the implications for sponsorship agreements when sporting events are cancelled

    Anna Sowerby

    In the Press

    min read
Back to top