• news-banner

    Expert Insights

Frustration under English law – Key issues in a global pandemic

min read

The extraordinary circumstances that Covid-19 has forced us to adapt to are demonstrated by the fact that we are routinely looking at an area of law which has developed, primarily, as a result of world changing events such as wartime shortages, the first Gulf War and the global financial crisis of 2008.

The extraordinary circumstances that Covid-19 has forced us to adapt to are demonstrated by the fact that we are routinely looking at an area of law which has developed, primarily, as a result of world changing events such as wartime shortages, the first Gulf War and the global financial crisis of 2008.

The extraordinary circumstances that Covid-19 has forced us to adapt to are demonstrated by the fact that we are routinely looking at an area of law which has developed, primarily, as a result of world changing events such as wartime shortages, the first Gulf War and the global financial crisis of 2008.

The extraordinary circumstances that Covid-19 has forced us to adapt to are demonstrated by the fact that we are routinely looking at an area of law which has developed, primarily, as a result of world changing events such as wartime shortages, the first Gulf War and the global financial crisis of 2008.

How does Frustration operate?
  1. Frustration discharges both parties from all of their future obligations pursuant to the contract.
  2. It operates automatically. It requires no positive act by either party.
  3. It requires there to have been an “outside event or extraneous change of situation” which has arisen without blame of the person seeking to rely on it.
  4. The key is whether the situation makes the obligation pursuant to the contract impossible to perform, not simply more difficult, or even financially catastrophic for one of the parties. 
  5. The circumstances that you must find yourself in have to be “radically different” from when the contract was concluded.
  6. The test has a high bar and requires you to prove that the contractual obligations have changed beyond what could have reasonably been anticipated at the time the contract was entered into. 
Key Points
  1. If the contract sets out what should happen in circumstances where there is a pandemic, a claim for frustration is likely to fail. The reason for this is that you are unlikely to get over the hurdle of finding yourself in a “radically changed” situation if such a circumstance (however unlikely) was considered at the drafting stage.
  2. The contract may provide an obligation for one party to insure against the risk. If so, the risk is likely to be deemed as having been assumed and again, frustration is likely to fail.
  3. Were the circumstances unforeseen and unforeseeable? This might be questionable where the contract has been entered into this year for example, after the outbreak of Covid-19 was announced. The courts have not yet considered the concept of whether, once announced, the spread was a likelihood and therefore foreseeable. Arguably, whilst a spread of the virus might have been likely, the magnitude of the interference and the damage that Covid-19 has caused could not have been foreseeable by anyone.
What contracts are most likely affected?
  1. Goods not being delivered.
  2. Services unable to be provided.
  3. Cancellation of events.

The key is that the performance of the contract becomes impossible. Note however that if the contract could be performed in a different manner, a claim for frustration is likely to fail.

Is the impossibility to perform temporary?

We can say with certainty that lockdown is temporary. That said, the duration of lockdown is uncertain as is whether its lifting will be phased and the likely incremental improvement of the economy.

Impossibility to perform will bite where you are looking at specific events which have had to be cancelled. The delay, however, isn’t always a “frustrating event” and if a part of a contract can be performed, then this must be considered. The key is whether it is proportionate to do so.

Illegality – is it illegal to perform it?

A prohibition which effects the main purpose of the contract is likely to be frustrated. The prohibition must however effect the means of performance for a claim for Frustration to be successful. If it can be carried out in a different manner, frustration will fail. It is also necessary to look at whether part of the contract survives, i.e. is it severable and still capable of performance? The extent of the effect of any illegality might be that any surviving clauses constitute a “radical change”. If so, the contract may be frustrated despite the possibility of the clauses being capable of severance.

Issues of public policy will also arise in circumstances where performance wouldn’t necessarily be illegal, but performance would not be in the interest of public policy because of the current restrictions.

What about if performance is now totally pointless?

There will be many contracts where parties have contracted to pay for goods or services for which they now have no use whatsoever. Arguably, the purpose of the contract has therefore been frustrated. Such an argument has rarely succeeded but the current circumstances may well see new cases on this point.

For example, Company A contracts to buy a new piece of machinery. Company A now has no need for that machinery. All of Company A’s factories are closed, all profits are now non-existent and the finance that Company A anticipated to obtain is no longer available. 

Performance of the contract is still possible. The fact that Company A now has no need for the machinery or the fact that it cannot obtain finance because of its lack of profits, is immaterial.

Conclusion

Covid-19 will undoubtedly result in an increase of frustration cases. Some will be clear cut such as the cancellation of events and supply contracts where time is of the essence. Where the situation is less clear, Covid-19 has demonstrated the importance of express contractual terms regarding force majeure and the allocation of risk to the parties. A cleverly drafted force majeure clause can allow for the suspension of obligations during temporary frustrating events, thus avoiding the potentially catastrophic consequences of frustration. In the absence of such a clause, the key will be whether any delay is sufficient to constitute the radical and fundamental change that frustration requires. 

A review of the scope of frustration of purpose also seems inevitable if we are to avoid a multitude of contracts being performed entirely unnecessarily, as a result of the commercial and economic consequences that Covid-19 has forced us to endure.

Our thinking

  • The Playbook to Superscale: Hacks 1-3

    Events

  • From Prime Time to Match Day: Engaging the Female Audience

    Events

  • Women in Leadership: In conversation with Wendy Edwards and Karen Ellis

    Claudine Morgan

    Events

  • eprivateclient features an article by Matt Foster and Sarah Moore on untangling crypto assets in divorce

    Matt Foster

    In the Press

    min read
  • Bloomberg Tax quotes Sally Ashford on the forthcoming HMRC requirement for lawyers to register as tax advisers

    Sally Ashford

    In the Press

    min read
  • Nicola Thorpe comments in The Telegraph on the importance of certainty for non-doms considering moving to the UK

    Nicola Thorpe

    In the Press

    min read
  • 10 ways the new APR/BPR rules affect estate administration

    Mary Perham

    Insights

    min read
  • ITV News interviews Ben Smith about a parliamentary debate around statutory menstrual leave

    Ben Smith

    In the Press

    min read
  • Clarification given by the Court of Appeal on rights of first refusal under the Landlord and Tenant Act 1987

    Natalie Deuchar

    Insights

    min read
  • Choosing the Right PISCES Platform for Private Company Liquidity

    Greg Stonefield

    Insights

    min read
  • How to construe contentious trusts - lessons from recent cases

    Sarah Moore

    Insights

    min read
  • Q&A: Modifying Restrictive Covenants

    Chandni Pandya

    Insights

    min read
  • RICS Property Journal features Chandni Pandya and Georgina Muskett on service charges for live/work units

    Chandni Pandya

    In the Press

    min read
  • Grid Connections, Environmental Assessment and the DCO Process – What is the effect of the Raeshaw Farms judgement?

    Kevin Gibbs

    Insights

    min read
  • Construction News and Facilities Management Now quote William Turner, Elizabeth Hughes, and Alexander Hemmings on new Construction Industry Scheme rules for supply chain fraud

    Elizabeth Hughes

    In the Press

    min read
  • Eddie Richards and Sadie Pitman write for Logistics Business on the UK's readiness for an electric vehicle revolution

    Sadie Pitman

    In the Press

    min read
  • Chiara Muston comments in People Management on 'empty time' and the gig economy

    Chiara Muston

    In the Press

    min read
  • Q&A: Boundary Issues

    Emma Preece

    Insights

    min read
  • Remedy and Leverage: Addressing Human Rights Risks in Corporate Supply Chains

    Kerry Stares

    Insights

    min read
  • Charles Russell Speechlys Partner Promotions 2026

    Bart Peerless

    News

    min read
Back to top