The Building Safety Levy comes into force – what developers need to know

min read

What is the Building Safety Levy? 

The Building Safety Levy is a new charge on major residential developments in England, established under powers in the Building Safety Act 2022 with detailed rules in the Building Safety Levy (England) Regulations 2025.  It is expected to raise approximately £3.4 billion towards remediation costs over the next ten years. 

Where does the Building Safety Levy apply?  

This Building Safety Levy will only apply in England.   

The Scottish building safety levy is planned to take effect in April 2028 under separate legislation, the Building Safety Levy (Scotland) Act 2026.  It is intended to raise between £360 million and £450 million over its 15 year period to provide funding for Scotland’s cladding remediation programme.

When does the Building Safety Levy come into effect?  

In England, the levy comes into effect on 1 October 2026.  Building control applications and initial notices submitted before that date (including where subsequently varied by an amendment notice or change control application) are not subject to the levy. 

It applies where: 

  • The works create new residential floorspace; 
  • The works are, or form part of, a “major residential development”; and 
  • The client is not an exempt person.  

A “major residential development” means at least 10 new dwellings, or 30 new bedspaces for purpose-built student accommodation (PBSA). For works to existing buildings (conversions, changes of use or extensions), existing dwellings or bedspaces are disregarded both for the threshold and the calculation.  

Whether works form part of a wider development is determined by the planning permission, to prevent attempts to avoid the levy by splitting a development into multiple building control applications below the threshold.

Which developments are exempt from the Building Safety Levy?  

Social housing and supported housing are exempt, as are non-profit registered providers of social housing and their wholly owned subsidiaries. Shared ownership dwellings and dwellings sold at first and subsequently for no more than 70% of market value can also qualify.

Other exempt accommodation includes: 

  • School accommodation, children’s homes, care homes and hospitals; 
  • Secure residential institutions, accommodation for victims of domestic abuse, and temporary accommodation for homeless people;  
  • Hotels, hostels, religious establishments and almshouses. 

How much is the Building Safety Levy?  

Rates vary by local authority area and are charged per square metre of Gross Internal Area. Illustrative rates include £100.35 per sqm in Kensington and Chelsea, £71.51 in Hackney, £50.87 in Cambridge, £24.57 in Leeds and £13.11 in Pendle. Developers operating within London and other wealthier areas should therefore expect to pay significantly more.  

Chargeable floorspace includes accommodation floorspace plus communal floorspace (stairways, lobbies, landings, plant rooms and other areas solely for occupants); a significant point for schemes with large communal areas such as build-to-rent, PBSA and retirement living.

A 50% brownfield discount applies where at least 75% of the land satisfies the previously developed condition, incentivising brownfield development.  Recent amendments to the meaning of ‘previously developed’ are discussed in Building Safety Levy: What Do the Proposed 2026 Amendments Mean? 

Who pays the Building Safety Levy?  

The client is liable to pay; where there is more than one named client, each is jointly liable.

How is the Building Safety Levy charged? 

The levy is charged through the local authority. To establish if the levy charging conditions apply and if there is an exemption: 

  • Initial levy information must accompany the building control application, initial notice or, for higher risk buildings, the gateway 2 application. 
  • Levy charging information is then provided at the time of issue of the commencement notice.   
  • Once the local authority has determined if the levy is due, it will either issue a levy liability notice or a notice of no charge. 
  • Where applicable, payment is due by the earlier of the ‘completion notice date’ and first occupation (disregarding any continuously occupied parts). No completion certificate or final certificate will be issued without payment. A review can be requested, with a right of appeal to the First-tier Tribunal.

The Government’s detailed guidance is available here. The exact process varies, depending upon the building control route (See process maps).

What about gateway 2 applications submitted before 1 October 2026? 

Developers who submitted gateway 2 applications for higher risk building works before 1 October 2026, hoping to avoid the levy, will be keen to see them approved.  For voided or rejected applications resubmitted on or after that date, the Regulations will apply. The latest data (12 weeks to 31 August 2026) shows a promising 92% approval rate for new build gateway 2 applications.

Next steps 

These continue to be challenging times for the industry, with developers also facing additional costs from: 

  • The two staircase requirement in force from 30 September 2026, targeting residential buildings of 18 metres or more (subject to transitional arrangements), and  
  • The Future Homes and Buildings Standards due 24 March 2027 (again subject to transitional arrangements).    

Developers will no doubt be reviewing their pipelines to assess which schemes will be subject to the levy, which may benefit from the 50% discount, and factor the charge into their appraisals.

There should be some good news ahead for housebuilders in London, with a consultation having closed earlier this month (September 2026) on proposed regulations to implement a new, time-limited relief from borough level Community Infrastructure Levy for qualifying developments in Greater London. 

For more developments and insights on Building and Fire Safety, please see here.  

Our thinking

  • Getting The Most From Your People

    Megan Paul

    Events

    min read
  • London Arbitration Week: ‘Building Data Centres Without Building Disputes’

    Gareth Mills

    Events

    min read
  • Construction Market Update: Looking Forward

    Michael O'Connor

    Events

  • Should You Even Bother? Making the Case for Bringing a Case

    Caroline Greenwell

    Events

    min read
  • Britain wants nuclear: Can we build it at pace?

    Kevin Gibbs

    Events

    min read
  • After the Confetti: Why the Real Work Begins the Day After Listing

    Greg Stonefield

    Insights

    min read
  • Investors’ Chronicle quotes Tamasin Perkins on how to avoid invalidating a will

    Tamasin Perkins

    In the Press

    min read
  • Ready for 2027: Legal Developments Shaping the Living Sector in England

    Mark White

    Insights

    min read
  • Q&A: Right to manage: can a landlord object on procedural grounds?

    Lauren Fraser

    Insights

    min read
  • Investing in London Real Estate Seminar

    Chiara Del Frate

    Events

    min read
  • Beds, Meds and Sheds: the beds haven’t gone – they’ve moved into houses

    Mark White

    Insights

    min read
  • Charles Russell Speechlys advises longstanding client SaxaVord Spaceport on its £30m investment from the UK government

    Charlie Ring

    News

    min read
  • Q&A: Recovering a freehold

    Sylwia Barchus

    Insights

    min read
  • Evidencing oral agreements: the weight of words

    Ben Moore

    Insights

    min read
  • Budget 2026: what the energy measures mean for generators, industry and investors

    Kevin Gibbs

    Insights

    min read
  • Nicola Saccardo comments on Italy’s proposed exit tax regime for wealthy individuals in The Daily Telegraph

    Nicola Saccardo

    In the Press

    min read
  • Loss of bargain on contract cancellation: no repudiatory breach required

    Mary Barrett-Jones

    Insights

    min read
  • ICLG quotes Dewdney William Drew on the High Court’s PINK trade mark ruling

    Dewdney William Drew

    In the Press

    min read
  • Amy Shuttleworth and Nicholas Wyatt write in RICS Property Journal about electric vehicle charging point leases

    Amy Shuttleworth

    In the Press

    min read
  • The Law Society Gazette quotes Kerry Stares on the development of the AI-powered Pro Bono Family Justice Hub

    Kerry Stares

    In the Press

    min read
Back to top