• news-banner

    Expert Insights

Providence v Hexagon: Supreme Court clarifies specified default and accrued rights of termination under a JCT Contract

min read

Yesterday, the Supreme Court handed down its judgment in the case of Providence Building Services Ltd v Hexagon Housing Association Ltd [2026] UKSC 1, reversing the Court of Appeal’s decision by concluding that, based on the objective and natural meaning of the clauses, a contractor cannot terminate its employment under clause 8.9.4 of the JCT Design and Build Contract (2016) unless it has accrued (but not exercised) a right to terminate their employment under clause 8.9.3.

Facts:

Hexagon (the Employer) and Providence (the Contractor) entered into an amended JCT Design and Build Contract (2016 edition) in February 2019, for the construction of a number of buildings in London (the Contract).

The Contract provided that if a specified default (including late payment of an amount due to the Contractor) continued for 28 days from the Employer’s receipt of a notice of specified default, the Contractor would be entitled to terminate their employment by further notice. Payment Notice 27 was due for payment on 15 December 2022. The Contractor served a notice of specified default (pursuant to clause 8.9.1 of the Contract), and the Employer paid in full on 29 December 2022.

Payment Notice 32 was due for payment on 17 May 2022.

The Employer did not make payment as required, and the Contractor issued a termination notice on the Employer on 18 May 2022, relying upon the Employer’s late payment of Payment Notice 27 as a repetition of a specified default. The Employer made full payment of Payment Notice 32 on 23 May 2022, and disputed the lawfulness of the Contractor’s termination notice.

The Employer referred the dispute to adjudication, after which the Contractor issued proceedings.

Submissions:

The Employer submitted that, as a condition of the Contractor issuing a termination notice under clause 8.9.4 of the Contract, the Contractor must first have accrued the right to serve such a notice under clause 8.9.3 (i.e. the Employer’s specified default must have remained ‘uncured’ within 28 days – that being the time period agreed between the parties in the Contract).

The Contractor argued that no such accrual was required, and that the Contractor was entitled to serve a valid termination notice following the Employer’s repetition of a specified default (and the Contractor’s valid serving of an earlier notice of specified default).

Judgment:

The Supreme Court found in favour of the Employer.

In reaching their unanimous decision, the Supreme Court considered:

  • the objective and natural meaning of the clauses in question, concluding that the interpretation by the Contractor (ie that the Contractor was entitled to immediately terminate their employment if the Employer made two late payments) was ‘extreme’.
  • that the direct reference in clause 8.9.4 to the Contractor not giving a termination notice under clause 8.9.3 made clause 8.9.4 ‘parasitic’, and clause 8.9.3 a ‘gateway’ to termination under clause 8.9.4.
  • that it was irrelevant that the Employer did not need to accrue a right to terminate in the event of the Contractor repeating a specified breach; it was found that this asymmetry was clearly the intention of the JCT drafter and the parties, on the basis that the base time periods specified by the parties were different, the references to compliance with other clauses were amended by the parties, and the unamended wording in clauses 8.4 and 8.9 were different.

What does this judgment mean in practice?

For employers, the judgment highlights the importance of ‘curing’ specified defaults within the periods specified within the contract, to avoid a contractor accruing the right to terminate. In this case, had the Employer failed to pay Payment Notice 27 within 28 days following receipt of the Contractor’s notice of specified default, the Contractor would have been entitled to validly terminate their employment upon the Employer’s failure to pay Payment Notice 32.

Given the wide-ranging use of the JCT Design and Build Contract (2016), and the fact that the current 2024 Edition uses the same wording, all those involved in the negotiation of standard form contracts (employers, contractors, and practitioners) should think carefully about the objective and natural meaning of the draftsman, and the importance of usual principles of contractual interpretation.

Our thinking

  • IBA Annual Conference 2026

    Jean-Baptiste Beauvoir-Planson

    Events

  • Surveyors' Refresher Seminar

    Hope Barton

    Events

    min read
  • Right to Work Reforms Webinar

    Kelvin Tanner

    Events

    min read
  • Caveat Venditor?: Fraudulent Misrepresentation in Sale and Purchase Agreements

    Emilie Brammer

    Insights

    min read
  • Easy come, easy go? A new consideration for temporary non-residents

    Christopher Gothard

    Insights

    min read
  • Restraint and Confiscation Orders in England and Wales

    Jana Billington

    Insights

    min read
  • Francis Ho writes in Building magazine about the process of remediation for residential buildings with unsafe cladding

    Francis Ho

    In the Press

    min read
  • Hannah Owen and Lydia Kember write in Family Law Journal on the intersection of trust law and surrogacy

    Hannah Owen

    In the Press

    min read
  • Shaanil Senarath-Dassanayake and Mike Barrington write in Finextra about regulatory themes every FCA-authorised fintech leader should be watching

    Shaanil Senarath-Dassanayake

    In the Press

    min read
  • Building Safety Update Seminar

    David Savage

    Events

    min read
  • Darren Bailey writes in City AM about what European football could learn from the US sports law landscape

    Darren Bailey

    In the Press

    min read
  • Charles Russell Speechlys recognised in Spear’s Legal Indices 2026

    News

    min read
  • Simon Ridpath features in the latest episode of the Non-Billable podcast

    Simon Ridpath

    In the Press

    min read
  • Private equity (PE): How Founders and Management Teams can protect themselves - it’s a marriage of convenience so make sure your pre-nup is watertight…

    Nadim Meer

    Insights

    min read
  • From Pilot to Nationwide Protection: New Powers to Protect Victims of Domestic Abuse

    Hilde Braaten Resseth

    Quick Reads

    min read
  • Lauren Fraser comments in New Law Journal on a Supreme Court decision regarding Right to Manage claims

    Lauren Fraser

    In the Press

    min read
  • What could the Law Commission’s proposals on the rights of first refusal mean for office occupiers?

    David Haines

    Insights

    min read
  • Birthright citizenship changes and US surrogacy: what UK and Swiss intended parents need to know

    Michael Wells-Greco

    Insights

    min read
  • Charles Russell Speechlys advises long-standing client BioMed Realty on Jagex's move to Granta Park

    Amy Shuttleworth

    News

    min read
  • Property Patter: Service Charges – What is the current state of play?

    Georgina Muskett

    Podcasts

Back to top