• news-banner

    Expert Insights

Providence v Hexagon: Supreme Court clarifies specified default and accrued rights of termination under a JCT Contract

Yesterday, the Supreme Court handed down its judgment in the case of Providence Building Services Ltd v Hexagon Housing Association Ltd [2026] UKSC 1, reversing the Court of Appeal’s decision by concluding that, based on the objective and natural meaning of the clauses, a contractor cannot terminate its employment under clause 8.9.4 of the JCT Design and Build Contract (2016) unless it has accrued (but not exercised) a right to terminate their employment under clause 8.9.3.

Facts:

Hexagon (the Employer) and Providence (the Contractor) entered into an amended JCT Design and Build Contract (2016 edition) in February 2019, for the construction of a number of buildings in London (the Contract).

The Contract provided that if a specified default (including late payment of an amount due to the Contractor) continued for 28 days from the Employer’s receipt of a notice of specified default, the Contractor would be entitled to terminate their employment by further notice. Payment Notice 27 was due for payment on 15 December 2022. The Contractor served a notice of specified default (pursuant to clause 8.9.1 of the Contract), and the Employer paid in full on 29 December 2022.

Payment Notice 32 was due for payment on 17 May 2022.

The Employer did not make payment as required, and the Contractor issued a termination notice on the Employer on 18 May 2022, relying upon the Employer’s late payment of Payment Notice 27 as a repetition of a specified default. The Employer made full payment of Payment Notice 32 on 23 May 2022, and disputed the lawfulness of the Contractor’s termination notice.

The Employer referred the dispute to adjudication, after which the Contractor issued proceedings.

Submissions:

The Employer submitted that, as a condition of the Contractor issuing a termination notice under clause 8.9.4 of the Contract, the Contractor must first have accrued the right to serve such a notice under clause 8.9.3 (i.e. the Employer’s specified default must have remained ‘uncured’ within 28 days – that being the time period agreed between the parties in the Contract).

The Contractor argued that no such accrual was required, and that the Contractor was entitled to serve a valid termination notice following the Employer’s repetition of a specified default (and the Contractor’s valid serving of an earlier notice of specified default).

Judgment:

The Supreme Court found in favour of the Employer.

In reaching their unanimous decision, the Supreme Court considered:

  • the objective and natural meaning of the clauses in question, concluding that the interpretation by the Contractor (ie that the Contractor was entitled to immediately terminate their employment if the Employer made two late payments) was ‘extreme’.
  • that the direct reference in clause 8.9.4 to the Contractor not giving a termination notice under clause 8.9.3 made clause 8.9.4 ‘parasitic’, and clause 8.9.3 a ‘gateway’ to termination under clause 8.9.4.
  • that it was irrelevant that the Employer did not need to accrue a right to terminate in the event of the Contractor repeating a specified breach; it was found that this asymmetry was clearly the intention of the JCT drafter and the parties, on the basis that the base time periods specified by the parties were different, the references to compliance with other clauses were amended by the parties, and the unamended wording in clauses 8.4 and 8.9 were different.

What does this judgment mean in practice?

For employers, the judgment highlights the importance of ‘curing’ specified defaults within the periods specified within the contract, to avoid a contractor accruing the right to terminate. In this case, had the Employer failed to pay Payment Notice 27 within 28 days following receipt of the Contractor’s notice of specified default, the Contractor would have been entitled to validly terminate their employment upon the Employer’s failure to pay Payment Notice 32.

Given the wide-ranging use of the JCT Design and Build Contract (2016), and the fact that the current 2024 Edition uses the same wording, all those involved in the negotiation of standard form contracts (employers, contractors, and practitioners) should think carefully about the objective and natural meaning of the draftsman, and the importance of usual principles of contractual interpretation.

Our thinking

  • Q&A: Signs and rights of way

    Oliver Park

    Insights

  • Conway v Conway: Proprietary Estoppel, Family Promises and the Limits of Informality

    Maddie Dunn

    Insights

  • Joe Edwards and Laura Bushaway write for Property Week on changes to possession actions

    Joe Edwards

    In the Press

  • New statutory guidance on the Modern Slavery Act 2015 for supply chains

    Kerry Stares

    Insights

  • The UK Supreme Court to consider whether adoption orders can be set-aside on the basis of welfare grounds

    Michael Wells-Greco

    Quick Reads

  • Autumn Budget 2025: Extension of Schedule A1 Inheritance Tax “look‑through” to UK agricultural property

    Sarah Wray

    Insights

  • Freezing Orders: how are they enforced around the world? England and Wales perspective

    Caroline Greenwell

    Insights

  • The Financial Times quotes Miranda Fisher on the rise in arbitration for divorces in England and Wales

    Miranda Fisher

    In the Press

  • Saudi Arabia’s 2025 Expropriation Law: What Has Changed?

    Ahmad Anani

    Quick Reads

  • Succession Planning in Family Investment Companies: What Should Families Consider?

    Mary Perham

    Quick Reads

  • Family Investment Companies: family values, succession and wealth stewardship

    Edward Robinson

    Quick Reads

  • Through the looking glass - transparency in the family courts (reprised).

    Charlotte Posnansky

    Quick Reads

  • Marcus Yorke-Long comments in Spears on the mediation of family wealth disputes

    Marcus Yorke-Long

    In the Press

  • The NPPF and an update on viability

    Sadie Pitman

    Quick Reads

  • The Results are in: AI on the Front Line of Alcohol Advertising Regulation

    Evie O'Connor

    Quick Reads

  • Technology Sector Lookahead 2026

    Mark Bailey

    Insights

  • Food & Beverage Lookahead 2026

    Rachel Bell

    Insights

  • AI in Advertising: A Regulatory Lookahead for 2026

    Willemijn Paul

    Insights

  • Payment Practices - the latest developments on reporting and late payments

    Willemijn Paul

    Insights

  • The Employment (Allocation of Tips) Act 2023 – practical impact since implementation

    Chiara Muston

    Insights

Back to top