• news-banner

    Expert Insights

Enhanced Remedies for Defective Work under the New UAE Civil Code: Article 818

min read

How Will the New Civil Code Change an Employer's Remedies When a Contractor Performs Defective Work During Construction?

Defective work during a construction project is one of the most common and commercially damaging disputes in the UAE construction sector. Under Federal Law No. 5 of 1985 ("1985 Civil Code"), the employer's remedies for defective work during execution have always been constrained by a requirement for prior court approval.

On 1 June 2026, Federal Decree-Law No. 25 of 2025 ("New Civil Code") will take effect, replacing the 1985 Civil Code in its entirety. Whilst not a mandatory rule, Article 818 fundamentally restructures the employer's remedies, introducing:

  • a formal warning and correction period mechanism, and
  • for the first time, permitting employers to terminate or appoint a replacement contractor without necessarily requiring prior court approval.

For parties to construction contracts in the UAE, whether based on FIDIC forms or bespoke agreements, this is a significant and practical reform.

The Current Position: Article 877 of the 1985 Civil Code

Article 877 provides that where a contractor performs defective work:

Irremediable defects

The employer may seek immediate rescission from the court.

Defects capable of remedy

The employer must first summon the contractor to rectify within a reasonable time. Only if the contractor fails may the employer apply to the court for rescission or authorisation to engage a replacement contractor at the defaulting contractor's expense.

Critically, both pathways require court approval. The employer cannot unilaterally terminate or engage a replacement without first obtaining a court order.

In practice, this has been a significant impediment to effective mid-project remediation. Court proceedings take time, during which defective work remains unaddressed, the programme suffers, and the employer faces considerable commercial uncertainty. As a consequence, employers will often tolerate substandard work rather than face the cost, delay, and uncertainty of court proceedings mid-project.

Article 818 of the New Civil Code: A Restructured Remedial Framework

Article 818 replaces Article 877 and introduces a materially different approach.

Performance obligations and gap-filling

Article 818(1) requires the contractor to perform in accordance with contractual terms and within the agreed period. Where the contract is silent, performance is governed by customary principles, and completion must occur within a reasonable period having regard to the nature of the works.

The formal warning and correction period

Where defective work is identified, the employer may issue a formal warning specifying the defect and granting a period for correction. If the contractor fails to remedy the defect within that window, the employer may terminate the contract or appoint another contractor at the defaulting contractor's expense. This introduces, for the first time, a structured escalation mechanism: formal notice, defined cure period, and then the right to act.

Reduced requirement for prior court approval

Article 818 does not explicitly require prior approval from the dispute resolution forum before the employer exercises its right to terminate or appoint a replacement following an unheeded warning. This is a significant departure from Article 877. The practical effect is to make mid-project remedies faster and more commercially viable. The removal of the express requirement does not mean employers have an unfettered right to act without judicial oversight. If there is a dispute over whether a defect or breach exists, the contractor can seek the court's input and protection. The shift is in the default position: the employer may act first, and the contractor's recourse is to challenge those actions after the fact.

Expanded grounds for immediate rescission

Article 818(3) expands the circumstances for immediate rescission without a cure period. Under Article 877, this was available only where remedial works were impossible. Article 818(3) adds further grounds:

  • where correcting the defects would be contrary to contractual terms;
  • where the contractor's delay makes timely completion "absolutely unlikely"; and
  • where the contractor's conduct indicates an intention not to perform.

These grounds reflect a more commercially realistic assessment of when employers need to act decisively.

Interaction with FIDIC Contracts

FIDIC contracts contain their own regime for defective work, including the Engineer's power to reject non-compliant work under Sub-Clause 7.5 and the employer's termination rights under Sub-Clauses 15.1/15.2 of the Red Book (1999 edition). It is noted however that Article 818 is not a mandatory rule.

As such, a FIDIC contract governed by UAE law will have both a contractual route and a statutory route to address defective work. The statutory route may be particularly valuable where contractual provisions are unclear, or where the contractor disputes the Engineer's assessment.

Practical Implications

For employers, Article 818 is a welcome reform. The ability to issue a formal warning and, if unheeded, to terminate or appoint a replacement without necessarily requiring prior court approval transforms a historically slow, court-dependent process into a more commercially effective remedy.

For contractors, the formal warning mechanism means an employer's dissatisfaction is now a statutory trigger with defined consequences. Contractors should ensure robust quality management systems, respond promptly to warnings, and document corrective actions thoroughly. There is also a risk that employers may use Article 818 opportunistically, issuing warnings as leverage in commercial disputes. Contractors should ensure any challenge is supported by contemporaneous evidence of compliance.

A practical obscurity in Article 818 is the concept of "appointing another contractor" without first terminating the original contract. On a live construction site, this is only realistic for discrete remedial works carried out by a specialist alongside the original contractor; for more extensive defects, the employer would ordinarily need to terminate before engaging a replacement to complete the works. The provision also leaves open questions of site coordination, insurance, and liability for defects in the replacement contractor's work, which should be addressed contractually.

Conclusion

Article 818 brings a long-overdue reform to employer remedies for defective work. The formal warning mechanism, reduced requirement for prior court approval, and expanded grounds for immediate rescission provide a more effective and commercially practical toolkit. The reform does not create an unrestricted right to terminate; procedural discipline is imposed on the employer, and courts retain an oversight role. The balance is between speed and fairness: enabling employers to act without the delays of prior court approval, whilst preserving the contractor's right to cure and to challenge the employer's decision. All stakeholders should review existing defects provisions and ensure contracts address the Article 818 framework before 1 June 2026.

This article is for general information only and does not constitute legal advice. Independent legal advice should be sought in relation to any specific matter.

Our thinking

  • IBA Annual Conference 2026

    Jean-Baptiste Beauvoir-Planson

    Events

  • The UAE's New Civil Code: Implications for Construction Contracts

    Maher Al Nashar

    Events

    min read
  • The Increased Expedited Procedure Threshold under the 2026 ICC Rules: What Does It Mean for Mid-Value Construction Disputes in the UAE?

    Glenn Bull

    Insights

    min read
  • Commonhold and Leasehold Reform Bill: Where are we now?

    Lauren Fraser

    Insights

    min read
  • Charles Russell Speechlys LLP, as Liquidator of Awal Bank BSC(c) (In Liquidation), welcomes Bahraini Court judgment upholding liquidator’s rejection of US$2.8 billion of claims and confirming debts owing to Awal Bank of US$2.56 billion

    Patrick Gearon FCIArb

    News

    min read
  • “Watt’s mine is yours” - environmental data sharing considerations for office occupiers

    Pippa Clifford

    Quick Reads

    min read
  • Can Contractors Resist Enforcement of an Adjudicator's Decision? Lessons from Kingsmead Homes v Laycock Mechanical Services [2025]

    Michael O'Connor

    Insights

    min read
  • The Fire Safety (Residential Evacuation Plans) (England) Regulations 2025: Implementation Stage

    Tegan Johnson

    Insights

    min read
  • New 2026 ICC Rules of Arbitration: what’s changed and what it means

    Thomas R. Snider

    Insights

    min read
  • Investing in the UK Living Sector? Here’s what the latest regulatory changes mean

    Sarah Wigington

    Insights

    min read
  • The Dubai Conflicts of Jurisdiction Tribunal Continues to Define the Boundaries of DIFC and Onshore Dubai Court Jurisdiction in Arbitral Award Recognition and Enforcement

    Thomas R. Snider

    Insights

    min read
  • Disputes Over Donuts: Spotlight on the ICC Arbitration Rules 2026

    Thomas R. Snider

    Podcasts

  • The New UAE Civil Code: A Series Overview

    Glenn Bull

    Insights

    min read
  • New details announced for the UK Government’s plan to ban cash retentions

    Kate Knox

    Insights

    min read
  • Naomi Nettleton writes in Estates Gazette about how the Renters' Rights Act is recalibrating the UK's rental property market

    Naomi Nettleton

    In the Press

    min read
  • Right to work changes: what they mean for Living Sector operators

    Emily McPartland

    Quick Reads

    min read
  • Mark White comments in CoStar on UKREiiF, private capital and real estate trends

    Mark White

    In the Press

    min read
  • Paula Boast MBE comments on the UK-GCC free trade agreement in Gulf Daily News

    Paula Boast MBE

    In the Press

    min read
  • David Savage and Lauren Fraser are quoted in PBC Today on the planned Building Safety Remediation Bill, and Commonhold and Leasehold Reform Bill

    David Savage

    In the Press

    min read
  • Switzerland plans further restrictions to buying real estate

    Oliver Schreier

    Quick Reads

    min read
Back to top