• news-banner

    Expert Insights

Collateral warranties: Liability and equivalent rights and defences clauses

min read

A recent Scottish case has provided clarification on the effect of clauses often included in collateral warranties: clauses which provide for no greater duties, no greater liabilities or equivalent rights and defences.  

In the case of Legal and General Assurance (Pensions Management) Ltd v The Firm of Halliday Fraser Munro and others, the Inner House, Court of Session (Scottish appeal court) upheld a decision rejecting the argument that collateral warranties incorporated the same defences, including any time-bar, available where a claim was made under the underlying contract.  

The case related to Union Plaza, a multi-story office building in Aberdeen, practical completion of which was achieved on 8 July 2008. Legal and General Assurance (Pensions Management) Ltd (L&G) later purchased the building in December 2013.

As part of the purchase, the architect, Halliday Fraser Munro (HFM) provided a collateral warranty in favour of L&G a few weeks later in January 2014.  

The collateral warranty notably included a clause stipulating that HFM owed no greater duties or obligations to L&G under the collateral warranty than would have been owed to L&G had they been named as the Client under the underlying appointment.

On 17 December 2018, L&G brought a claim against HFM and others in relation to alleged defects in the building, such as basement water ingress and corrosion/paint protection to steel. On 2 February 2021, L&G made a further claim in relation to alleged fire protection defects relating to soffit insulation.

HFM argued that both claims had been brought out of time as a consequence of claims under the underlying appointment being time barred as a consequence of more than five years having elapsed since the date of practical completion. The first instance court rejected HFM’s arguments and HFM appealed to the Inner House.

The issues considered by the Inner House on appeal were:

Issue 1: Was the commercial judge correct to hold that it was immaterial that the collateral warranty post-dated L&G’s acquisition of the building?

HFM argued that there was no recoverable loss because the collateral warranty was entered into after L&G bought the building.  This was argued on the basis that L&G sustained loss at the time when they bought the building in its damaged condition; any breach of the collateral warranty did not cause (and could not cause) L&G to suffer loss.

The Inner House did not hesitate to reject this argument, finding that it failed to give effect to the clear terms and underlying purpose of the collateral warranty.  As was made clear by the wording of the duty of care clause included in the collateral warranty, HFM had warranted to L&G that they had performed their duties as architects under their appointment with reasonable skill and care.  In effect, they undertook or promised that they had done so.

Issue 2: Is the time-bar under the collateral warranty the same as under the original underlying contract?

HFM relied on a previous Inner House decision, British Overseas Bank Nominees Ltd v Stewart Milne Group Ltd [1] to argue that the inclusion of a “no greater duties” clause in a collateral warranty was sufficient to incorporate a contractual time-bar corresponding to the conventional prescriptive period which applied to the underlying appointment.  In the British Overseas Bank case, the collateral warranty featured such a clause.  HFM argued that such a clause went not just to the scope of the duties or obligations owed by the consultant; it also encompassed the duration of those duties or obligations.  

The Inner House rejected this argument holding that a collateral warranty is a standalone contract and that defences and time limits from the underlying contract are not impliedly imported. Only an express clause conferring “equivalent rights and defences” from the underlying contract will align any time bar, and where this is not express, time runs from the date of the collateral warranty.

The Court distinguished this case from the British Overseas Bank case where the collateral warranty contained not only an express “no greater liability” clause but also an “equivalent rights and defences” clause which anchored the time bar to the underlying contract. In this case, the “no greater duties” clause in HFM’s collateral warranty addressed equivalence of duties; it did not deal with equivalence of defences. 

Consequently, the Court determined that, in the absence of a contractual limitation provision, the earliest possible date for commencement of the five-year short negative prescriptive period applicable in Scots Law would be the date when the collateral warranty was granted.

The Court also went on to consider whether HFM’s conduct induced L&G into error so as to suspend prescription under section 6(4) of the Prescription and Limitation (Scotland) Act 1973 (the Act).  On this point, the Court held that L&G’s December 2018 claims against HFM were within the five years period from the date of the collateral warranty and so were not time‑barred, however, L&G’s later claims introduced in February 2021, regarding the fire protection defects relating to soffit insulation, fell outside five years from the warranty date and were not saved by section 6(4) of the Act.

Drafting points

This case is widely regarded as a landmark decision under Scots Law and may be persuasive in the English Courts. The decision aligns with views taken in leading practitioners’ textbooks such as Hudson’s Building and Engineering Contracts in which it commented that, in the absence of an express time limit in a collateral warranty, the collateral warranty may create a series of fresh causes of action at the date of the warranty.  

Parties entering into collateral warranties will want to carefully consider the issue of duration of contractual liability and how this is addressed in the collateral warranty’s terms, particularly where collateral warranties are being issued long after practical completion.  Fundamentally, a “no greater duties” clause limits the scope/standard of duty but, on its own, will not import the defences or time limits from the underlying contract.

[1] [2020] SC 24

Our thinking

  • IBA Annual Conference 2026

    Jean-Baptiste Beauvoir-Planson

    Events

  • Surveyors' Refresher Seminar

    Hope Barton

    Events

    min read
  • Right to Work Reforms Webinar

    Kelvin Tanner

    Events

    min read
  • Building Safety Update Seminar

    David Savage

    Events

    min read
  • Lauren Fraser comments in New Law Journal on a Supreme Court decision regarding Right to Manage claims

    Lauren Fraser

    In the Press

    min read
  • What could the Law Commission’s proposals on the rights of first refusal mean for office occupiers?

    David Haines

    Insights

    min read
  • Birthright citizenship changes and US surrogacy: what UK and Swiss intended parents need to know

    Michael Wells-Greco

    Insights

    min read
  • Charles Russell Speechlys advises long-standing client BioMed Realty on Jagex's move to Granta Park

    Amy Shuttleworth

    News

    min read
  • Property Patter: Service Charges – What is the current state of play?

    Georgina Muskett

    Podcasts

  • World Trademark Review quotes Robert Lundie Smith on the High Court’s $11.6 million damages award to Swatch

    Robert Lundie Smith

    In the Press

    min read
  • Charles Russell Speechlys appoints Justine Howard as General Counsel

    Justine Howard

    News

    min read
  • Niamh Tenison contributes to an Estates Gazette legal Q&A on limitation periods and incorrect court fees

    Niamh Tenison

    In the Press

    min read
  • Hannah Catt writes in PrimeResi on the upcoming High-Value Council Tax Surcharge in the UK and why it needs careful design

    Hannah Catt

    In the Press

    min read
  • The latest UK-Switzerland Services Deal: Is it a Game-Changer for Cross-Border Mobility?

    Paul McCarthy

    Quick Reads

    min read
  • No Easy Escape: The Court confirms test to restrain a call on an on-demand performance bond

    Sara Cunningham

    Insights

    min read
  • Qatar’s New Preliminary Registration Framework: A Transformative Step for the Off-Plan Market

    Ahmad Anani

    Insights

    min read
  • CasinoBeats quotes Darren Bailey on player betting bans and sports gambling partnerships

    Darren Bailey

    In the Press

    min read
  • Kerry Stares, Rory Partridge and Lyla Gilbert write in Sustainable Views about how sustainable packaging is becoming a condition of EU market access

    Kerry Stares

    In the Press

    min read
  • William Longrigg writes in the Law Society Gazette on the potential return of Calderbank offers in family proceedings

    William Longrigg

    In the Press

    min read
  • Pay Up or We'll Tell All: The High Court's Firm Stance on Blackmail in Privacy Cases

    Hannah Gornall

    Quick Reads

    min read
Back to top