• news-banner

    Expert Insights

IET’s new revision 7 of the Model Form of Contract (MF/1): What has changed?

10 years after the publication of Revision 6 (2014 edition) of the Model Form of Contract for the design, supply and installation of electrical, electronic and mechanical plant (MF/1), the Institution of Engineering and Technology (IET) has released Revision 7 (2024 edition), shortly followed by an erratum containing a summary of corrections.

Regular users of the MF/1 may be comforted to know that the risk profile of the contract has not changed though the door has been opened to extending the duration of liability for latent defects, as discussed below.  

Here is an overview of some of the more notable changes:

Extensions of time (EoT)

The grounds for EoTs have not changed substantially.  The EoT for industrial disputes has been qualified to exclude disputes restricted to between the Contractor and its employees and/or the Contractor’s subcontractors (Clause 33.1(c)).  Interestingly, the IET have not chosen to include drafting specifically on epidemics, the Contractor instead needing to rely upon the force majeure type wording in clause 33.1(d); something which the JCT have chosen to expressly include in some of the JCT 2024 Editions now being published.

Liability for Latent Defects

At the end of Defects Liability Period, the Contractor is released from all liability save for correction of latent defects notified within a latent defects liability period.  Revision 6 had expressly provided for that latent defects liability period to be 3 years after the date of taking-over of the works (Clause 36.10).  

During that period, the Contractor is required to repair or replace the latent defect, at its option.  Notably there is no provision for the Purchaser to itself remedy a latent defect or arrange for others to do so and recover its costs from the Contractor.  With the exclusive remedies clause (clause 44.4), recovery of these costs is prevented.  This is an issue Purchasers will need to give careful consideration to.

Under Revision 7, the parties have free rein to specify the duration of the latent defects liability period in the Appendix.  

This potentially ties in with another change made to Revision 7:

  • allowing the parties to sign the contract as a deed (rather than as a simple contract allowed for under Revision 6).  
  • Allowing for the template forms of bonds and guarantees to be signed as deeds (rather than as a simple contract allowed for under Revision 6).  

Professional indemnity insurance (PII)

Revision 7 now requires the Contractor to maintain PII in the amount and for the duration specified in the Appendix (Clause 47.5) though the drafting doesn’t include the more often seen proviso that such insurance is available in the market on reasonable rates and terms; something that Contractor’s may seek in view of the more often volatile insurance market.

Adjudication

To give effect to the statutory right to adjudicate pursuant to the Housing Grants, Construction and Regeneration Act 1996 (as amended), Revision 6 had contained an optional Special Condition 2 which allowed for the parties to refer a dispute to adjudication, with the decision being binding until finally determined by legal proceedings, arbitration or by agreement.  

That drafting has now moved into the General Conditions in Revision 7 (Clause 53) unless the International Contracts Schedule is applied, when it is omitted. 

Slavery, Bribery and Corruption

With the introduction of the Modern Slavery Act 2015 after the last revision (albeit the Bribery Act 2010 was some time before), Revision 7 now includes new clauses 54 (Anti-Slavery and anti-human trafficking) and clause 55 (Anti-bribery and anti-corruption) to be complied with by the Contractor.

Termination for Force Majeure

The definition of Force Majeure remains the same in Clause 46.1, with the IET again choosing not to follow the JCT’s lead of including dedicated epidemic drafting.  

Revision 7 does now qualify either party’s right to terminate the contract (after either party has not performed any of its obligations for a continuous period of 120 days because of an event of Force Majeure) by carving out the situation where the Corporate Insolvency and Governance Act 2020 (CIGA) applies (Clause 46.3).  CIGA restricts the rights of a supplier of services to terminate its contract where the recipient is insolvent.  

There is also now included a window of just 21 days after the expiry of the 120 day period when a termination notice may be issued.

Termination for the Contractor’s default (Clause 49.1):

Timescales have been shortened:

  • The Contractor has 14 days (rather than the previous 30 days) after receiving the Engineer’s written notice to commence suspended works in the absence of a reasonable excuse.
  • The Purchaser may give 14 days’ notice (rather than the previous 21 days) of its intention to terminate the contract on the occurrence of the Contractor’s default events listed in clause 49.1 (though it is an immediate notice if it is on the ground of the Contractor’s insolvency).  

There are new Contractor default grounds for breaches of the anti-slavery and anti-human trafficking provisions (clause 54) or anti-bribery and anti-corruption provisions (clause 55).

Termination for the Purchaser’s default

The Contractor’s right to terminate is made subject to CIGA.  

The description of what constitutes insolvency has been expanded to include recent changes in insolvency legislation; now also including where a moratorium is applied for or is entered into pursuant to Part A1 of the Insolvency Act 1986 or any step is taken in relation to a scheme of arrangement under Part 26 or Part 26A of the Companies Act 2006 (Clause 51.1)

International Projects

Revision 7 introduces an ‘International Contract Schedule’ intended to enable users to omit certain UK-specific provisions contained in the General Conditions in order for it to be more readily used on overseas projects.  In such cases, the parties should seek advice on the local laws applicable to their projects.

General

In common with the JCT 2024 editions currently being published, the IET have introduced gender neutrality and updated notice provisions, in this case omitting reference to faxes.

What haven’t they included?

  • Construction (Design and Management) Regulations 2015: there is no provision for the Contractor to be appointed either as the principal designer or principal contractor under these regulations.
  • Dutyholders Regime under Part 2A of the Building Regulations 2010: again no reference to the Contractor being appointed for the roles of the principal designer or principal contractor under these regulations.
  • Despite giving the parties the option to extend the duration of the latent defects liability period, surprisingly, there is still no provision for collateral warranties from either the Contractor or any of its subcontractors.  
  • Could the contract embrace more themes from the Construction Playbook such as including a greater emphasis on collaborative working or sustainable development or the trend towards mediating disputes?  

Our thinking

  • IBA Annual Conference 2025

    Simon Ridpath

    Events

  • Next Gen Rural Professionals Drinks Reception

    Events

  • Triple Play "Bid Fever": UK Tech's ability to scale and go global

    Mark Howard

    Quick Reads

  • The Future of AI and Copyright Regulation in the UK: The Data (Use and Access) Bill finally gets Lords approval in the UK

    Rebecca Steer

    Quick Reads

  • HM Land Registry's Digital Drive - Delays Persist but perhaps there is light at the end of the tunnel?

    Maisy-Jane Cook

    Quick Reads

  • Key aspects of the FCA’s PISCES Sourcebook

    Jodie Dennis

    Insights

  • Mike Barrington and Mary Perham write for Tax Adviser on what the proposed changes to business property relief mean for investors and entrepreneurs, and for their businesses

    Mike Barrington

    In the Press

  • Bloomberg quotes Catrin Harrison on the recent exodus of non-doms from the UK

    Catrin Harrison

    In the Press

  • Trusts and Matrimonial Disputes in England

    Tom Watts

    Insights

  • The Financial Times and Daily Mail quote Emma Humphreys on the impact of the UK Government's Spending Review on housebuilding targets

    Emma Humphreys

    In the Press

  • Alumni Drinks Reception

    Events

  • Consultation on Private International Law and Digital Assets Law Commission Proposes Landmark Reforms

    Racheal Muldoon

    Insights

  • Navigating International M&A Disputes: Insights and Strategies for 2025

    Stephen Burns

    Quick Reads

  • Bridging Differences: The Role of Mediation in Resolving Cross-Border Trust Disputes

    Tamasin Perkins

    Insights

  • Planning essentials case update: what changes can I make to my listed building?

    Sadie Pitman

    Quick Reads

  • Rachel Warren writes for Solicitors Journal on the new failure prevent fraud offence

    Rachel Warren

    In the Press

  • MoneyWeek quotes Mary Perham on whether business property relief can be claimed on a furnished holiday let

    Mary Perham

    In the Press

  • Anti-greenwashing in the UK, EU and the US: the outlook for 2025 and best practice guidance

    Caroline Greenwell

    Insights

  • Landmark rulings from the Italian Revenue Agency on income tax exemption on gains from Italian shares held in trust

    Nicola Saccardo

    Quick Reads

  • Sowing doubt: slashing green farm funding is a risk we can't afford

    Maddie Dunn

    Quick Reads

Back to top