• news-banner

    Expert Insights

Omitting works from an NEC contract: Valuation under the contractual mechanism

The recent decision in Van Oord v Dragados [2020] CSOH 87, is a useful reminder to parties to construction contracts about the potential dangers of varying the scope of works under the contract and how such variations may be assessed under the contract, in particular under an NEC form of contract.

Background

Dragados was the main contractor for the design, management and construction of the Aberdeen Harbour expansion. Van Oord was engaged by Dragados as its subcontractor to complete the soft-dredging works under the NEC3 form of subcontract (Option B).

As the works progressed through 2018 and 2019, Dragados began to instruct the omission of certain works from the scope of Van Oord’s subcontract. The works were not simply omitted, but were given to another sub-contractor to complete. As a result, Van Oord was denied not only the opportunity to carry out a significant portion of its works but its profit on those works.

The matter went to adjudication with the adjudicator finding largely in favour of Dragados.

‘Defined Cost’ under NEC v bill of rates?

Dragados argued that the compensation events mechanism was appropriate for all compensation events, including breaches of contract. As the omission of works constituted a compensation event under the NEC subcontract, Dragados claimed that this reduced the total amount payable to Van Oord for the remaining works to be carried out. The amount payable for the works which remained should be valued on the basis of the ‘Defined Cost’ (the actual costs), rather than the amounts included in Van Oord’s bill of rates.

Van Oord commenced court proceedings and contended, among other things, that:

  • Dragados was not entitled to give the work omitted from Van Oord’s scope of work to another sub-contractor;
  • this amounted to a breach of contract; and
  • Dragados was not entitled to reduce the amount payable to Van Oord, rather payment should have been made on the basis of the original bill of rates.

The decision

In relation to the first issue, Lord Tyre in the Scottish Court of Sessions did not identify a contractual entitlement for Dragados to omit the works and transfer them to another sub-contractor. The Court noted that even if the variations clause provides for omissions to be made from the scope of works, this does not necessarily mean they can be given to a third party to complete.

The principles identified in the English decision in Abbey Developments Limited v PP Brickwork Limited [2003] EWHC 1987 (TCC) were followed in this case, namely:

  1. The contractor has a duty to carry out the work and has the right to complete the work;
  2. Variation clauses must be considered carefully, so as not to deprive the contractor of their right to complete the work – there must be wording entitling an omission of work and giving it to another contractor; and
  3. The reason or motive behind the omission is irrelevant. The entitlement to omit work and give it to another to complete all turns on whether the contractual clause allows for the change.

The Court also identified that there was a breach, being the instruction to change the Subcontract Works Information by way of the omission of works. Despite it being a breach, the omission of works was considered to be a ‘compensation event’ under the NEC subcontract, meaning that it would fall to be considered within the compensation event mechanism. The Court held that this was the only method of assessment, even if it resulted in Van Oord being entitled to a reduction in payment.

Lord Tyre identified that the use of the compensation calculation in the NEC subcontract, which is based on identifying the ‘Defined Costs’, was a more objective way of giving effect to the change to the scope of works, including a change that occurs as a result of a breach of contract.

Going forward

It is unsurprising that the court held that omitting the scope of works and giving these works to another party was a breach of contract. However, parties to construction contracts, in particular an NEC form of contract should take note of the court’s use of the contractual compensation mechanism as a means of assessing the consequences of omitting works. Just because the instruction, i.e. the omission of works, resulted in a breach of contract, this did not prevent it from also being a change to the subcontract which should then be assessed in accordance with the contractual mechanism.

This decision highlights the fact that contractual compensation mechanisms may not work in your favour, even in circumstances where the other party has breached the contract.

Although this was a Scottish decision, it is more widely relevant as the NEC contracts are used extensively across the UK. Care should be taken when it comes to drafting and negotiating variation clauses. If changes to the scope of works are envisaged, ensure that the contract properly provides for this so that the affected contractor (or subcontractor as in this case) is no better or worse off.

This article was written by Anna Sowerby and Eveline Strecker. For more information, please contact Anna.

Our thinking

  • Advocacy: Lessons from The Mandela Brief for International Arbitration Today

    Jue Jun Lu

    Events

  • LIIARC Tax Investigations Uncovered: Legal Tactics, Courtroom Trends & Strategic Remedies

    Caroline Greenwell

    Events

  • Updates from the Building Safety Regulator - Unblocking the Gateways for Higher Risk Buildings

    Tegan Johnson

    Quick Reads

  • Insights from the latest ABA Technology in M&A Subcommittee meeting – where are recent innovations taking us?

    Daniel Rosenberg

    Quick Reads

  • World Intellectual Property Review quotes Dewdney William Drew on the Getty Images vs Stability AI decision

    Dewdney William Drew

    In the Press

  • The 1975 Act Turns Fifty: Why Reform was Needed and What Changed

    Tamasin Perkins

    Insights

  • ECCTA for Charities: Maintaining Registers

    Giverny McAndry

    Insights

  • ECCTA 2023 - Failure to prevent fraud offence- what charities need to know and do

    Penelope Byatt

    Insights

  • What do agricultural landlords and workers need to know about the Renters’ Rights Act?

    Emma Preece

    Insights

  • An introduction to Economic Crime and Corporate Transparency Act 2023 for charities: key changes from 18 November 2025

    Liz Gifford

    Insights

  • Succession Stumbling Blocks: Lessons from Thomas v Countryside Solutions Ltd

    Maddie Dunn

    Quick Reads

  • Morning Star UK quotes Julia Cox on the impact of potential inheritance tax rises in the UK Autumn Budget

    Julia Cox

    In the Press

  • What legal developments can the Living Sector expect as we approach the end of 2025 and look ahead to 2026?

    Mark White

    Insights

  • CDR Magazine quotes Jue Jun Lu on China’s newly revised arbitration law

    Jue Jun Lu

    In the Press

  • Andrew Ross and Laura Bushaway write for Property Week on a Supreme Court judgment relating to nuisance

    Andrew Ross

    In the Press

  • Good Divorce Week 2025: Believe it or not, there is a better way

    Emily Borrowdale

    Quick Reads

  • Charles Russell Speechlys further bolsters its Corporate team with the appointment of Ed Morgan

    David Collins

    News

  • Autumn Budget 2025: Sifting the Rumours on Tax Rises and Reforms

    Charlotte Inglis

    Quick Reads

  • Adjudication under the Construction Act – a case on the residential occupier exception and contesting the validity of a payless notice

    Tegan Johnson

    Insights

  • VAT on Developer’s Biodiversity net gain (BNG) costs

    Elizabeth Hughes

    Insights

Back to top