• news-banner

    Expert Insights

Hybrid contracts - Should payment notices distinguish between sums due for construction operations and non-construction operations?

Hybrid contracts are one of the more unusual creatures arising from the Housing Grants, Construction and Regeneration Act 1996. They are contracts that include both “construction operations” (as defined in the Act) and works which are excluded from the operation of the Act. They have given rise to a number of cases considering how the statutory right to adjudicate applies to such contracts. Lord Justice Coulson referred to this as a “self-inflicted problem” which the courts must do their best to resolve until the Act is amended to do away with these “unnecessary distinctions”.

In the recent decision of C Spencer Limited v M W High Tech Projects UK Limited, the Court of Appeal considered hybrid contracts again in the context of the payment provisions in the Act.

Background

MW High Tech Projects UK Limited was the main contractor appointed for the design and construction of a power plant capable of processing refuse-derived fuel produced by waste. C Spencer Limited was engaged as MW’s sub-contractor to design and build the civil, structural and architectural works for the facility. The sub-contract price was over £35 million.

The sub-contract was substantially comprised of works falling within the definition of “construction operations” for the purposes of the Act. However, the works also included the assembly of plant and erection of steel to provide support or access to plant and machinery. Such works are expressly excluded from the definition of “construction operations” in the Act.

The sub-contract provided for milestone payments and included an Act compliant payment mechanism that did not distinguish between “construction operations” and “non-construction operations”.

A dispute arose in relation to a payment application submitted by C Spencer. This payment application made a distinction between construction and non-construction operations. It allocated approximately £2.6 million plus VAT to construction operations and provided a breakdown of that figure.  However, MW issued a payment notice which stated that C Spencer actually owed MW approximately £6.8 million excluding VAT.  MW’s payment notice (in line with previous payment notices) did not distinguish between construction and non-construction operations.

C Spencer argued that this was not a valid payment notice and therefore the sum they had applied for was due by default. The key point to this argument was that the payment notice was not valid because it did not distinguish between construction and non-construction operations. C Spencer commenced Part 8 proceedings seeking payment of approximately £2.6 million on this basis.

The Court’s decision

The issue for the Court was therefore whether a payment notice under a hybrid contract had to distinguish between “construction operations” and non-construction operations in order to be valid?

The Court of Appeal agreed with the TCC that this was not the case and so dismissed C Spencer’s claim on the basis that:

  • There was nothing in the sub-contract which required the parties to differentiate between construction and non-construction operations in their payment or payless notices.
  • Analysis must start with the contract terms in order to see if they comply with the Act. The Act envisages that the parties will contract on terms agreed between them. If those terms comply with the Act, the Act is no longer of relevance to the parties. The Act envisaged hybrid contracts but did not go on to say that hybrid contracts should require separate or distinct notification of sums due for construction operations. It could have done so. The contract therefore complied with the Act.
  • Parties are free to agree a payment mechanism for their contract that sits alongside the statutory provisions. In other words, they can “contract in” to the Scheme for Construction Contracts (which operates under the Act), but they cannot “contract out” of the Act for construction operations. In practice, this is commonly adopted in sub-contracts which include both construction and non-construction operations in certain industries. Lord Justice Coulson went on to say “that approach is not only permissible, it is to be welcomed”. It provides certainty and transparency and avoids the complications that having two separate payment regimes would bring. 

The Court of Appeal also found that the importance of the distinction between construction and non-construction operations under a hybrid contract only arises if there is a dispute over the sum due. Unless it is extended by agreement between the parties (which it had not been in this case), an adjudicator will only have jurisdiction to deal with disputes relating to construction operations under the construction contract.

What does this mean for hybrid contracts?

It is likely that parties will continue to use one payment mechanism for hybrid contracts. This means the payment provisions needs to be compliant with the Act, otherwise the Act will imply the relevant provisions from the Scheme for Construction Contracts to replace any non-compliant terms in the payment mechanism for the construction operations only. This would result in two payments mechanisms in the contract.

The Act does not require payment applications or notices to distinguish between construction and non-construction operations.

The Act will only imply a right to adjudicate into the contract in respect of the construction operations. A party will therefore only be able to bring an adjudication claim in respect of the non-construction operations if there is a contractual right to do so. If not, any adjudication that does not clearly confine itself to the construction operations could be subject to a jurisdictional challenge. In such circumstances, the claiming party will have to make sure that the application subject to the adjudication claim clearly differentiates the sums applied for in respect of construction operations.  Otherwise, it will be difficult to establish that there is a dispute in relation to the sums claimed for those specific items of work and that the adjudication claim only relates to sums due in respect of construction operations.

This article was written by Associate Katherine Keenan. For more information, please contact Katherine on +44 (0)20 7427 6512 or at katherine.keenan@crsblaw.com.

Our thinking

  • IBA Annual Conference 2025

    Simon Ridpath

    Events

  • Alumni Drinks Reception

    Events

  • London International Disputes Week: Trusts hurt: the fraud lawyer, the trust, and the avenues of attack (and defence)

    Tamasin Perkins

    Events

  • London International Disputes Week: Navigating International M&A Disputes: Insights and Strategies for 2025

    Stephen Burns

    Events

  • Government publishes consultation on Regulations about how rent is calculated under the Landlord and Tenant Act 1954 for agreements with Code operators

    Georgina Muskett

    Quick Reads

  • ESG Duties for Directors: Legal Obligations and Risks Under English Company Law

    Katie Bewick

    Insights

  • Conclusive truth or abusive sleuth - can covert recordings be used in family law proceedings?

    Charlotte Posnansky

    Insights

  • UK Real Estate Opportunities for Asia Capital

    Simon Green

    Events

  • Law Commission publish their recommendations for reform on Wills

    Charis Thornton

    Quick Reads

  • What does the UK Immigration White Paper mean for businesses, families and entrepreneurs?

    Paul McCarthy

    Insights

  • BBC News quotes Emma Preece on a Supreme Court decision around whether people can camp in certain areas of Dartmoor without permission from landowners

    Emma Preece

    In the Press

  • From Tradition to Transaction - The Rise of Private Equity in Family Businesses in the Middle East

    Ahmad Anani

    Insights

  • The UK’s immigration white paper – what does it mean for British Nationals (Overseas)?

    Owen Chan

    Quick Reads

  • Directors’ Disqualification Under the Company Directors Disqualification Act 1986: What UK Directors Need to Know

    Claudine Morgan

    Insights

  • The Financial Times quotes Catrin Harrison on IHT Budget changes and the impact on wealthy UK expats

    Catrin Harrison

    In the Press

  • Property Patter: Applications to discharge or modify restrictions

    Emma Humphreys

    Podcasts

  • Should access be given between exchange and completion?

    Twiggy Ho

    Insights

  • What next for the hydrogen sector?

    Rachael Davidson

    Quick Reads

  • UK Cybersecurity and Resilience Policy Statement April 2025 - Impacts for Managed Services Providers and Data Centres

    Mark Bailey

    Insights

  • Covenant modified by Tribunal to allow office redevelopment in accordance with planning permission

    Georgina Muskett

    Insights

Back to top