• news-banner

    Expert Insights

Essential law: Variations - Part two

Continuing our series on the basics of construction law, Sara Cunningham considers some of the issues that can arise when valuing variations under a construction contract.

Variations may give rise to additions or deductions from the contract sum and may also require an adjustment to the completion date, depending on the nature and scale of the variation. The key starting point when valuing a variation is the terms of the relevant construction contract.

How are variations valued?

Generally speaking, there are two approaches to the valuation of variations:

  • Using contractual rates
  • Valuing on a cost basis.

Different standard forms take different approaches. For example, the JCT forms generally seek to value variations using the contractual rates, whereas the NEC forms generally seek to value variations on a cost basis.

Using contractual rates

Valuing variations is most often based on the rates and prices in the contract. For example, the valuation rules in the JCT design and build form provide the following process to value variations:

  • Where work is of a similar character to work in the contract documents, then the valuation shall be consistent with the relevant values in the contract sum analysis.
  • There will be a due allowance for any change in the conditions under which the work is carried out or the quantity of the work, together with an allowance for any addition or omission of design work and for any change to the provision of site administration, site facilities and temporary works.
  • Where the work cannot be valued on the above basis, the valuation can be carried out on a time and resource basis – in other words, a dayworks valuation.
  • In so far as a dayworks valuation cannot be made, a “fair” valuation is to be made.
  • In so far as a variation leads to a substantial change in the conditions under which any other work is executed, that other work shall also be treated as varied and valued in accordance with the above principles.
  • Any effect of the variation on the regular progress of the works is to be ascertained separately under the loss and expense clause.

Valuing on a cost basis

An alternative approach is to value variations on a cost basis.

For example, the NEC contracts do not value variations (one of the compensation events under the NEC forms) by reference to the contract prices. Instead, they are valued by:

  • Assessing the effect of the variation on the defined cost (not actual cost) of the works. This defined cost is assessed by reference to the relevant schedule of cost components, which sets out the items to be included in the defined cost. It is not necessarily the same as the actual cost incurred by the contractor in carrying out the variation.
  • Adding a percentage uplift to that change in defined cost to represent the fee (meaning the contractor’s overheads and profit).

This assessment is to include all the effects of a variation. In other words, there is no separate valuation of loss and expense resulting from any effect on the progress of the works.

Further, the parties can agree to use the contractual prices to value a variation if they consider that more appropriate.

Common issues

There are a number of issues that can arise when valuing variations:

  • Should the valuation always include an allowance for overheads and profit? In Weldon Plant vs Commission for the New Towns (2001), the court considered a contract based on the ICE conditions and whether a fair valuation could be made that excluded an allowance for overheads and profit. The court held that a fair valuation had to establish which overheads were involved in the variation and had to include an element of profit in the absence of special circumstances.
  • What if the contractual rates are too high or too low for the variation? If the contract provides that the variation is to be valued using these rates, this could lead to a windfall for one of the parties. This is one of the reasons the NEC adopts a cost-based valuation for variations – it is intended that no party should unfairly gain as a result of a variation.
  • How should omitted works be valued? This will always depend on the terms of the contract. In MT Højgaard vs E.ON (2017), the court agreed with the contractor’s argument that the omission should be valued by reference to the contribution of the omitted work to the total contract price. It rejected an argument from the employer that the valuation should be based on an estimate of what it would have cost the contractor had it carried out the works as originally planned.

This article was written by Sara Cunningham and was first published in ‘Building’ magazine on 3 June 2020.

Our thinking

  • IBA Annual Conference 2024

    Charlotte Ford

    Events

  • Record number of leading individuals for Charles Russell Speechlys in Chambers High-Net-Worth 2024

    Piers Master

    News

  • Collateral Warranty and Third Party Rights: Everything You Need to Know

    Chris Marks

    Insights

  • Supreme Court overturns Court of Appeal decision: Statutory adjudication will not apply to a typical collateral warranty

    Kevin Forsyth

    Insights

  • IET’s new revision 7 of the Model Form of Contract (MF/1): What has changed?

    Melanie Tomlin

    Insights

  • From Manchester to the Metaverse: How United’s Roblox Rollout Could Help Drive Fan Engagement

    Shennind Awat-Ranai

    Insights

  • FCA announce new UK Listing Rules coming into force on 29 July 2024

    Jodie Dennis

    Quick Reads

  • New UK Listing Rules to be implemented 29 July 2024

    Victoria Younghusband

    Insights

  • Darren Bailey and Frédéric Jeannin write for City AM on geopolitical risk and challenges posed to Paris by staging the Olympic Games

    Darren Bailey

    In the Press

  • Inside Housing quotes James Walton on the potential financing impact of delays at the Building Safety Regulator

    James Walton

    In the Press

  • IFLR quotes Victoria Younghusband on new UK listing rules unveiled by the FCA

    Victoria Younghusband

    In the Press

  • Bloomberg quotes Sarah Jane Boon on plans announced in the King’s speech to press ahead with the tax hike on UK private school fees

    Sarah Jane Boon

    In the Press

  • CoStar quotes Claire Fallows and Ben Butterworth on some of the key real estate issues addressed in the King's Speech

    Claire Fallows

    In the Press

  • “We want prenup! We want prenup!” (Yeah!)

    Cara Fung

    Quick Reads

  • Charles Russell Speechlys reports domestic and international growth across all practice areas

    Simon Ridpath

    News

  • Cyber Co-ordination 2024 - new MOU on co-operation between EBA, ESMA, EIOPA and ENISA

    Mark Bailey

    Insights

  • The EU AI Act: A Beginner’s Guide for UK and International Businesses using AI

    Janine Regan

    Insights

  • James Walton writes for the Evening Standard on whether the Government can expect a return on its new National Wealth Fund

    James Walton

    In the Press

  • ADGM Court holds that NMC can bring fraudulent and wrongful trading claims retroactively

    Nicola Jackson

    Quick Reads

  • Citywealth quotes Robert Blower and Oliver Little on the intersection between trust structures and Sharia law

    Robert Blower

    In the Press

Back to top