• news-banner

    Expert Insights

Essential law: Variations - Part one

In the first of a series on the basics of construction law, James Worthington and Vanessa Jones begin with variations, considering here the scope of the right to instruct variations.

The variations regime is fundamental to both parties to a construction contract. It gives the employer the flexibility to change the works, and determines the extent to which the contractor will be allowed additional time and money for such changes.

This article will look at some of the issues regarding the extent of the employer’s right to instruct a variation and the contractor’s right to claim that an employer’s instruction is a variation.

What is a variation?

Most construction contracts will include a definition of what is a “variation” under that contract. In general terms, a variation is an instruction by the employer to alter the works to be performed or an instruction to vary their timing, method or sequence.

However, not all instructions will be treated as variations. In particular:

  • Where the instructed work is “indispensably necessary” to complete the contract works, the court will generally infer that it is included in the contracted works, regardless of the fact that it is not expressly identified in the specification. 
  • Where the contractor has agreed to design and build a facility to meet certain performance specifications, changes to the design required to meet those performance specifications will generally not be a variation.
  • Where the contractor has taken on a risk under the contract (such as ground conditions), any delay or additional cost that arises from that risk will be the responsibility of the contractor, and will generally not be a variation even though the methodology required to complete the works may have changed.
  • Where the contract gives the architect the power to determine the method by which the works are executed, it is generally not a variation if the architect chooses a specific methodology, even if that choice was unreasonable.

Can an employer instruct any variation?

There are certain limits on the employer’s right to instruct a variation that will generally be implied into a construction contract, such that the following are not permitted (unless expressly permitted by the contract or agreed by the contractor):

  • Instructions that fundamentally change the nature of the contract, or were clearly not contemplated by the original contract. The guiding principle is that after such variation the works should still be capable of being identified as the works originally defined in the contract.
  • Instructions that omit works for the purpose of awarding those works to another contractor. If an employer intends to omit work, it should be for the purpose of omitting that work entirely from the project. The courts have held that a contractor has both an obligation to do the works, and a corresponding right to be able to do those works.
  • Instructions after practical completion has already occurred. 

Does the contractor have the right to carry out additional work? 

A contract may give the employer the right to instruct additional work, but that does not mean there will be an implied term that if additional work is required, the employer must instruct the contractor to carry it out.

Can the contractor object to a variation?

This would depend on the terms of the relevant variation clause. However, the standard forms generally contain a limited right for the contractor to object. For example, JCT provides that a contractor may make a reasonable objection to an instruction that relates to the imposition by the employer of any restrictions regarding access, limitations of working space or working hours or the execution of work in a specific order.

Are there circumstances where an employer is obliged to instruct a variation?

Certain standard form contracts (such as the old ICE conditions) place a positive obligation on the engineer to instruct a variation if this was necessary for completion. However, whether such an obligation may be implied is more complex. There is a tension between the contractor’s obligation to build what is described in the contract even if that is impossible, and the implied duty on the employer to co-operate.

What if there is no variation clause?

All standard form construction contracts contain variation clauses, but what if the parties have contracted on, say, a simple agreement of price and scope of work without a variations clause?

First, there is no implied right for an employer to instruct a variation under a construction contract. Therefore if there is no express contractual right for an employer to instruct variations, the contractor can refuse to carry out such variations without consequence.

Second, if the contractor agrees to carry out such variation, this varied work may be construed as a new contract such that the varied work is valued on a different basis than under the original contract and not based on the rates and prices in that original contract.

This article was written by James Worthington and Vanessa Jones at Charles Russell Speechlys and was first published in ‘Building’ magazine on 5 March 2020.

Our thinking

  • Key Developments in International Arbitration for 2026

    Dalal Alhouti

    Quick Reads

  • Agricultural policy review 2025: Key changes and what to expect in 2026

    Maddie Dunn

    Insights

  • Leasehold and Freehold Reform Act 2024: Government launches consultation to switch on provisions relating to estate management charges

    Laura Bushaway

    Quick Reads

  • M&A in UK financial services - will mega-deals in 2025 lead to more mid-market activity in 2026?

    Mike Barrington

    Quick Reads

  • A new prospectus regime and other developments impacting UK Equity Capital Markets in 2026

    Andrew Collins

    Insights

  • The Introduction of Aquis Support Services – 19 January 2026

    Emily Dobson

    Insights

  • POATR - What type of securities does the new regime apply to?

    Emily Dobson

    Quick Reads

  • Infosecurity Magazine quotes Mark Bailey on the Cyber Security and Resilience Bill

    Mark Bailey

    In the Press

  • Hannah Catt writes for Tax Adviser on the implications of the newly introduced high value council tax surcharge in the UK

    Hannah Catt

    In the Press

  • eprivateclient quotes Dominic Lawrance on rumours surrounding potential UK government plans to attract HNW investors

    Dominic Lawrance

    In the Press

  • UK Living Sector 2026: Regulatory pressures, new trading platforms and more accessible public markets

    Sarah Wigington

    Insights

  • A Family Lawyer’s guide to five of the top most Googled Family Law questions in England and Wales relating to children

    Hannah Owen

    Quick Reads

  • Drip Pricing and Enforcement: How the DMCC Act is Changing the Rules

    Mark Dewar

    Insights

  • The Standard quotes William Marriott on the impact of the newly introduced 'mansion tax' in the UK

    William Marriott

    In the Press

  • Amenity Space in UK Office Buildings: Why It Matters and What Tenants Need to Consider

    Lynsey Inglis

    Insights

  • UK Hotels Sector 2026: Renovations, AI and Experience‑Led Stays

    James Broadhurst

    Insights

  • Charles Russell Speechlys grows Real Estate team with the appointment of UK and Italian market expert Chiara Del Frate

    Robin Grove MIoL

    News

  • Investment Week quotes Greg Stonefield on whether 2026 will be the year of London IPOs

    Greg Stonefield

    In the Press

  • Compliance Week quotes Abigail Rushton on the UK’s anti-corruption strategy and compliance lessons for companies and advisors

    Abigail Rushton

    In the Press

  • When Saying “No” to Mediation Is Reasonable: Guidance from Grijns v Grijns

    Bella Preece

    Quick Reads

Back to top