    Expert Insights

COVID-19: time and money under JCT

Unsurprisingly 2019 novel coronavirus disease (COVID-19) and its impact on construction contracts has been a key concern for our clients recently. Many of those clients use a JCT form of contract, usually with amendments.

Existing contracts

The immediate concern for live projects is delays caused by shortages in goods and materials (just try importing Italian marble at the moment) or delays in importing them, as well as potentially a lack of labour. Two relevant events are, well, relevant: the exercise by the government of a statutory power and force majeure.

Taking the first, under the JCT Standard Building Contract, 2016 Edition (or the Design and Build form) a claim in respect of a Relevant Event requires both the exercise of a statutory power and a power that directly affects the execution of the works. Government guidance/recommendations alone are unlikely to suffice. At the time of writing there has not been a formal government intervention in the UK such as those seen in Italy and the US and so the first of these is not in play, as yet!

As for force majeure, there is no settled definition under English law and the JCT contracts do not define it or give examples. Perhaps the next edition of JCT contracts will now do so. That said, force majeure is generally understood to cover circumstances that are not within a contracting party’s control and authority suggests it would cover epidemics. On that basis it is difficult to see how the outbreak would not constitute a force majeure event.

It is common for contracts to exclude a shortage of goods or materials arising from force majeure and under those contracts the contractor has assumed the risk. In our experience of acting for employers and contractors, many employers are considering taking a pragmatic approach and seeking a risk share agreement rather than necessarily enforcing the contractual terms favourable to them. Of course this will require buy-in from funders and end-users. It would be unrealistic to expect an employer to do otherwise.

Delay damages

What about the money? In the unamended JCT, the contractor takes the entire risk of loss and expense due to the impact of COVID-19 on the progress of its works. At least they do in theory. In our experience, employers are including this risk as part of their commercial discussions and seeking relief from delay damages. Again, what do the employers’ funders think? They hold the purse strings after all.

Suspension

What happens if the works are suspended? In the JCT there is a mutual right of termination where the works or substantially the whole of the works are suspended for a period of two months as a result of force majeure or the exercise of a statutory power, among others. Given the present state of affairs in Italy, it is not inconceivable that construction projects could be so significantly disrupted that these termination provisions could be engaged.

Presumably both parties would like to extend that qualifying period of suspension – another item for the commercial discussions.

Future contracts

In contracts under negotiation, both employers and contractors must address the issue directly and allocate the risk between the parties. Parties do not necessarily have a free hand here. Interestingly, we are seeing funders refuse to lend unless the contractor assumes the risk. If most contractors simply refuse, will we see a re-think?

It is not just that there are obvious benefits in setting out the position clearly: remaining silent could have unintended consequences. The more foreseeable the consequences of an event are, the more difficult it is to demonstrate that the event constitutes force majeure – the rationale being that it would be “reasonable” to expect a contractor to be able take steps to avoid or mitigate the consequences of that event.

There are also other considerations. Is it fair for the entire risk of COVID-19 to sit with one party, whether that be time and/or money? Is a risk share more reasonable? What will the employer’s funder agree to? What is palatable to an end-user?

Also, how do you define COVID-19? What about mutations of it? Including a widely defined event is not always best, even from a contractor’s perspective. The looser the definition the more difficult it may be for a contractor to evidence that the delay is caused by that event.

What about shortage of labour? Parties may want to distinguish between a shortage caused by the numbers of workers being ill or prevented from working due to a government order and pre-emptive measures that a contractor might choose to bring in to avoid the spread of the disease. Is it fair that a contractor who takes sensible precautionary steps for the wider good is to be penalised for doing so?

Employers will want their contractors to be proactive in managing delay as specified materials are sourced or manufactured abroad. A potential option could be to include a positive obligation on a contractor to make design proposals to mitigate the impact, something that could be added to the value engineering provisions or design submission procedure.

Termination?

Should COVID-19 lead to termination? Should the qualifying suspension period be extended to avoid the risk of termination? This is all the more reason why it is important to properly address the effects of delay at the outset.

We suspect there is much more to come on this topic.

This article was written by Fiona Edmond & Christopher Busaileh. For more information please get in touch via fiona.edmond@crsblaw.com or christopher.busaileh@crsblaw.com

A version of this blog was first published by Practical Law Construction on 17 March 2020

Our thinking

  • Modernising Business Tenancies: Where and how should disputes be heard?

    Andrew Ross

    Insights

  • Broker duties, lender liability and secret commission: broking bad

    Rebecca Hollinshead

    Insights

  • The Telegraph quotes Henry Fea on the changes to inheritance tax breaks and the likely impact on family farms in the fictional BBC radio drama 'The Archers'

    Henry Fea

    In the Press

  • Hydrogen Hurdles: navigating the path to net zero in the UK

    Rachael Davidson

    Insights

  • The Law Society Gazette quotes Joe Cohen and Aileen Johnson in a feature on ‘GenAI two years on’

    Joe Cohen

    In the Press

  • Navigating UK Financial Services Regulation: A Guide for Insolvency Practitioners

    Daniel Moore

    Insights

  • Tamasin Perkins writes for the Financial Times’ Your Questions column on succession planning

    Tamasin Perkins

    In the Press

  • An Overview of the Court of Arbitration for Sport

    Benoît Pasquier

    Insights

  • A company can claim privilege against its own shareholder

    Emilie Brammer

    Insights

  • Radiotelevisione svizzera (RSI) interviews Sophie Dworetzsky on the UK non-dom tax changes and the appeal of Switzerland

    Sophie Dworetzsky

    In the Press

  • Tamasin Perkins writes for Wealth Briefing on the assisted dying bill and lessons from financial abuse claims

    Tamasin Perkins

    In the Press

  • A range of titles including the Financial Times, Daily Telegraph and The Times quote Claire Fallows on M&S receiving approval to demolish its flagship Oxford Street store

    Claire Fallows

    In the Press

  • Neurodiversity and the Law: Creating a Supportive Work Environment

    Briony Richards

    Insights

  • The EU Deforestation Regulation: an update and what it means for companies

    Kerry Stares

    Insights

  • Computer says no [update] - border chaos delayed until April 2025

    Paul McCarthy

    Quick Reads

  • The New UK Net Zero Carbon Buildings Standard 2024 – an ESG milestone?

    Tegan Johnson

    Insights

  • The United Arab Emirates – Seeking Remedies for Financial Crime

    James Colautti

    Insights

  • Navigating Cross-Border Bankruptcy: The UK Supreme Court’s Judgment in Kireeva v Bedzhamov [2024] UKSC 39

    Bianca Venkata

    Insights

  • Adverse Possession of Land: Key Points for Landowners, Developers and those working in Strategic Land

    Emma Preece

    Insights

  • The Law Society Gazette quotes Tamasin Perkins on the assisted dying bill

    Tamasin Perkins

    In the Press

Back to top