• news-banner

    Expert Insights

Hacking through the JCT Payment Mechanism and Adjudication?

min read

In the leading judgment in the Court of Appeal’s decision in Grove Developments v S&T dealing with “smash and grab” adjudications, Sir Rupert Jackson observed:

“We are all trying to hack out a pathway through a dense thicket of amended legislation, burgeoning case law and ever-changing standard form contracts”.

But having hacked through this thicket, has Sir Rupert cleared the pathway only to find another thicket for the JCT interim payment mechanism?

A reminder of the facts

Grove engaged S&T under a JCT Design and Build Contract 2011 (with certain amendments). Near the end of the works, an interim payment dispute arose and S&T commenced an Adjudication seeking payment of the applied for sum of c£14M.  S&T argued Grove had failed to issue a valid payless notice and therefore the sum applied for had become the certified sum and payable. 

Grove argued that it had served a valid payless notice – the first adjudicator decided it had not - but also commenced a second adjudication seeking a “true valuation” of the interim account. 

Grove refused to pay the £14M and sought declarations from the High Court that its payless notice was valid and that it could commence a second adjudication on the “true value” in any event.

Coulson J decided the payless notice was valid and therefore there was no obligation to pay the £14M.  Coulson J also went on to decide that even if there was no valid payless notice, Grove had the right under the Contract and the Housing Grants Construction and Regeneration Act 1996 as amended (the Act) to commence the second “true value” adjudication.

The Court of Appeal’s Decision

The Court of Appeal expressly endorsed Coulson J’s decision, confirming:

  • Interim ‘certified sums’ were provisional and not conclusive as to the “true value” of work done;
  • An adjudicator, arbitrator, judge has wide powers to open up any certified sums where those sums are disputed. 
  • An employer could commence a second “true value” adjudication
  • An employer may recover “any overpayment” made at an interim stage and the adjudicator must be able to “…give effect to the financial consequences of his decision.”
  • The Act and the contract prohibit an employer from embarking on the “true value” adjudication before he has complied with the obligation to make payment.

Analysis / Comment

Whilst the implications of this case will still need to be worked through – including whether the judgment brings about the end of smash and grab adjudications – (my view is that it will not), the judgment arguably creates a potential conflict with the Act and interim payment mechanism of JCT contracts.

Under JCT interim payment mechanisms (unlike the NEC suite of contracts) there is no right or obligation on the Contractor to make an interim / balancing payment to the Employer where there is a negative interim certificate.

Where there had been previous overvaluations, the normal course is for the certificate to certify the negative sum and state there was a “nil” balance due that month. The expectation was there would then be an adjustment in later certificates.

Although the Court of Appeal was not concerned with the recovery of potential historic overpayments (Grove acknowledged that c£276,000 was due to S&T), in deciding that an employer can recover “any overpayment” and that the adjudicator has the power to give effect to the financial consequences of his decision, it is arguable that the Court of Appeal’s decision does give employers a right of repayment for historic over certification and not just the overpayment arising from the failure to issue a payment or payless notice.

Whilst Sir Rupert Jackson acknowledged that there was no express provision under the JCT wording permitting negative interim payments, he noted that s111 of the Act (the obligation to pay the certified sum) applied to both interim and final payments.  Section 111 of the Act refers to “payers” and “payees” of interim and final payments and therefore a contractor could be a “payer” at both interim and final payment stages. 

He further noted that the Court of Appeal had determined in the case of Harding v Paice that an employer has the right to challenge the notified final payment (where he had failed to issue a payment or payless notice) commenting “…it would be strange if that same form of words [under section 111] has a conclusive effect in relation to interim certificates which it does not have in relation to final certificates…” and affirming the analysis that “If an adjudicator finds that the employer has overpaid at an interim stage, he can order re-payment of the excess…”

This analysis does appear to create a tension between the express wording (and agreement of the parties) under a JCT contract and the interpretation of payment obligations under the Act.  Perhaps more importantly it runs the risk of counteracting the Act’s widely acknowledged policy of promoting cashflow, although users of NEC suite of contracts will be well accustomed to this scenario.

It will be interesting to see how the courts and adjudicators, as well as the JCT drafting committee, hack away at this thicket in the future.

Our thinking

  • High Court interprets repair covenant in Hotel lease and statutory fire safety obligations

    Chandni Pandya

    Insights

    min read
  • Be Careful What You Wish For: In the UAE, How a Tenant’s Force Majeure Claim Can Dissolve Its Own Lease

    Glenn Bull

    Insights

    min read
  • Building safety update: Progress on future changes, including the recategorisation of certain higher risk building works

    David Savage

    Insights

    min read
  • Drapers quotes Cara Imbrailo on out-of-town retail parks and fashion retailers' need for space

    Cara Imbrailo

    In the Press

    min read
  • Georgina Muskett contributes to PropLaw on the Landlord and Tenant Act and opposing lease renewal on the ground of redevelopment

    Georgina Muskett

    In the Press

    min read
  • Lauren Fraser comments in PropLaw on reforms to property ownership in the UK through commonhold tenure

    Lauren Fraser

    In the Press

    min read
  • Sadie Pitman writes in CoStar about the development of hyperscale data centres

    Sadie Pitman

    In the Press

    min read
  • Rebecca Morjaria is quoted in the press about our role advising Mulalley & Co. in a successful £1.8m Building Safety claim

    Rebecca Morjaria

    In the Press

    min read
  • Cara Imbrailo comments in Property Week, on how to unlock supply during a shortage of retail park space

    Cara Imbrailo

    In the Press

    min read
  • Nicola Saccardo speaks to TopLegal on the growth of Charles Russell Speechlys’ Italian practice

    Nicola Saccardo

    In the Press

    min read
  • Recalibrating England’s rental market: The Renters’ Rights Act

    Naomi Nettleton

    Insights

    min read
  • Back-to-back is not enough: UAE construction subcontracts and multiparty arbitration under the 2026 ICC Rules

    Glenn Bull

    Insights

    min read
  • Estates Gazette Q&A: Redevelopment break clauses

    Matt Cordwent

    Insights

    min read
  • Charles Russell Speechlys advises Mulalley & Co. in successful £1.8m Building Safety claim

    Rebecca Morjaria

    News

    min read
  • Mulalley v Sto: Germany cladding product supplier found 87.5% responsible in contribution claim

    Rebecca Morjaria

    Insights

    min read
  • Sarah Keens comments in Property 118 about how banning upward-only rent reviews could create instability in England's rental market

    Sarah Keens

    In the Press

    min read
  • Questions on rights of light

    Georgina Muskett

    Insights

    min read
  • Solving renters’ rights conundrums

    Laura Bushaway

    Insights

    min read
  • Leaseholder Remediation (Building Safety) Bill: What developers and landlords need to know

    Richard Flenley

    Insights

    min read
  • Charles Russell Speechlys advises Lauralu's management on its sale to Eurazeo

    Stéphane de Lassus

    News

    min read
Back to top