• news-banner

    Expert Insights

Hacking through the JCT Payment Mechanism and Adjudication?

In the leading judgment in the Court of Appeal’s decision in Grove Developments v S&T dealing with “smash and grab” adjudications, Sir Rupert Jackson observed:

“We are all trying to hack out a pathway through a dense thicket of amended legislation, burgeoning case law and ever-changing standard form contracts”.

But having hacked through this thicket, has Sir Rupert cleared the pathway only to find another thicket for the JCT interim payment mechanism?

A reminder of the facts

Grove engaged S&T under a JCT Design and Build Contract 2011 (with certain amendments). Near the end of the works, an interim payment dispute arose and S&T commenced an Adjudication seeking payment of the applied for sum of c£14M.  S&T argued Grove had failed to issue a valid payless notice and therefore the sum applied for had become the certified sum and payable. 

Grove argued that it had served a valid payless notice – the first adjudicator decided it had not - but also commenced a second adjudication seeking a “true valuation” of the interim account. 

Grove refused to pay the £14M and sought declarations from the High Court that its payless notice was valid and that it could commence a second adjudication on the “true value” in any event.

Coulson J decided the payless notice was valid and therefore there was no obligation to pay the £14M.  Coulson J also went on to decide that even if there was no valid payless notice, Grove had the right under the Contract and the Housing Grants Construction and Regeneration Act 1996 as amended (the Act) to commence the second “true value” adjudication.

The Court of Appeal’s Decision

The Court of Appeal expressly endorsed Coulson J’s decision, confirming:

  • Interim ‘certified sums’ were provisional and not conclusive as to the “true value” of work done;
  • An adjudicator, arbitrator, judge has wide powers to open up any certified sums where those sums are disputed. 
  • An employer could commence a second “true value” adjudication
  • An employer may recover “any overpayment” made at an interim stage and the adjudicator must be able to “…give effect to the financial consequences of his decision.”
  • The Act and the contract prohibit an employer from embarking on the “true value” adjudication before he has complied with the obligation to make payment.

Analysis / Comment

Whilst the implications of this case will still need to be worked through – including whether the judgment brings about the end of smash and grab adjudications – (my view is that it will not), the judgment arguably creates a potential conflict with the Act and interim payment mechanism of JCT contracts.

Under JCT interim payment mechanisms (unlike the NEC suite of contracts) there is no right or obligation on the Contractor to make an interim / balancing payment to the Employer where there is a negative interim certificate.

Where there had been previous overvaluations, the normal course is for the certificate to certify the negative sum and state there was a “nil” balance due that month. The expectation was there would then be an adjustment in later certificates.

Although the Court of Appeal was not concerned with the recovery of potential historic overpayments (Grove acknowledged that c£276,000 was due to S&T), in deciding that an employer can recover “any overpayment” and that the adjudicator has the power to give effect to the financial consequences of his decision, it is arguable that the Court of Appeal’s decision does give employers a right of repayment for historic over certification and not just the overpayment arising from the failure to issue a payment or payless notice.

Whilst Sir Rupert Jackson acknowledged that there was no express provision under the JCT wording permitting negative interim payments, he noted that s111 of the Act (the obligation to pay the certified sum) applied to both interim and final payments.  Section 111 of the Act refers to “payers” and “payees” of interim and final payments and therefore a contractor could be a “payer” at both interim and final payment stages. 

He further noted that the Court of Appeal had determined in the case of Harding v Paice that an employer has the right to challenge the notified final payment (where he had failed to issue a payment or payless notice) commenting “…it would be strange if that same form of words [under section 111] has a conclusive effect in relation to interim certificates which it does not have in relation to final certificates…” and affirming the analysis that “If an adjudicator finds that the employer has overpaid at an interim stage, he can order re-payment of the excess…”

This analysis does appear to create a tension between the express wording (and agreement of the parties) under a JCT contract and the interpretation of payment obligations under the Act.  Perhaps more importantly it runs the risk of counteracting the Act’s widely acknowledged policy of promoting cashflow, although users of NEC suite of contracts will be well accustomed to this scenario.

It will be interesting to see how the courts and adjudicators, as well as the JCT drafting committee, hack away at this thicket in the future.

Our thinking

  • UK Real Estate Opportunities for Asia Capital

    Simon Green

    Events

  • PBC Today quotes Kevin Gibbs on amendments to the Planning and Infrastructure Bill

    Kevin Gibbs

    In the Press

  • Michael O'Connor and Lauren Fraser write for Property Week on the impact of the Building Safety Act on residential property management

    Michael O'Connor

    In the Press

  • Martyn’s Law receives Royal Assent – what do property owners and occupiers need to do now?

    Ben Butterworth

    Quick Reads

  • Can Labour deliver 1.5m new homes?

    David Savage

    Insights

  • Setting Standards: The Ciarb Guideline on AI Use in Arbitration

    Dalal Alhouti

    Insights

  • Risky Business: Lessons in clearing up Contractual Confusion in John Sisk and Son Ltd v Capital & Centric (Rose) Ltd

    Murron McKeiver

    Insights

  • TCC decision on validity of payment and payless notices served simultaneously

    Johnathon Grasso

    Insights

  • Property Patter: “It’s the economy, stupid”

    Emma Humphreys

    Podcasts

  • Developers Granted (Temporary) Reprieve: Building Safety Levy Postponed To Autumn 2026

    Ashley Williams

    Insights

  • Property Wire quotes Ben Butterworth on Martyn's Law receiving Royal Assent

    Ben Butterworth

    In the Press

  • Building Safety and the challenges for UK construction - where are we now?

    David Savage

    Events

  • Energising Infrastructure: Key Infrastructure Reforms in the Latest Planning & Infrastructure Bill

    Kevin Gibbs

    Insights

  • Nick Hurley and Erin Hughes write for Personnel Today on two recent constructive dismissal tribunal cases

    Nick Hurley

    In the Press

  • Michael O'Connor writes for Construction News on the potential impact of Building Liability Orders (BLOs) on the construction sector

    Michael O'Connor

    In the Press

  • Steven Carey and Amelia Hamilton respond to a reader's question in Construction Management relating to PFI contracts in schools

    Steven Carey

    In the Press

  • Joanne Searle writes for CMM Magazine on the potential for Government support of the social care sector

    Joanne Searle

    In the Press

  • Building BioHubs miniseries: Carter Jonas

    Lynsey Inglis

    Podcasts

  • Adjudicators can hear legacy building safety defect claims: BDW Trading Limited v Ardmore Construction Limited [2024] EWHC 3235

    Melanie Tomlin

    Insights

  • The first case on Information Orders in connection with Building Liability Orders: BDW Trading Limited v. Ardmore Construction Limited & Ors

    Ogooluwa Esther Michael-John

    Insights

Back to top